Standard Direct Labor Cost The controller at your shoemaking company has determined that under normal conditions, you pay your employees $8.40 per hour, and it will take 2.6 hours of labor per pair of shoes. Given this information, calculate the standard cost of labor per pair of shoes. If required, round the standard labor per pair shoes to the nearest cent. Manufacturing Costs Standard Price x Standard Hours per Pair = Standard Cost per Pair Direct Labor per hour hours Feedback Check My Work Use the standard price and standard hours values shown to compute the standard labor cost per pair. Actual Direct Labor Cost During August, your shoe-making company incurred actual direct labor costs of $62,211 for 6,990 hours of direct labor in the production of 2,175 pairs of shoes. Given this information, calculate the actual cost of labor per hour. If required, round the actual cost of labor per hour to the nearest cent. Manufacturing Costs Actual Total Cost Actual Total Hours Actual Cost per Hour Direct Labor hours
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
Answer)
Calculation of Standard Cost of Labor per Pair of Shoes
Standard Cost of Labor per pair of Shoes = Standard rate per labor hour X Standard Labor hours per pair
Standard Cost of Labor per pair of Shoes = $ 8.40 per labor hour X 2.60 Labor hours per pair
Standard Cost of Labor per pair of Shoes = $ 21.84 per pair of Shoes
Final Answer: Standard Labor cost per pair of Shoes is $ 21.84.