solve the questions: Tony and his team identified some risks during the first month of the Recreation and Wellness Intranet Project. However, all they did was document the risks in a list. They never ranked the risks or developed any response strategies. Because the project has had several problems, such as key team members leaving the company, users being uncooperative, and team members not providing good status information. Tony has decided to be more proactive in managing risks. He also wants to address positive risks as well as negative risks. the quation is : 1- Plot the six risks on a probability/impact matrix. 2- assign a numeric value for the probability and impact of each risk on meeting the main project objective.
solve the questions:
Tony and his team identified some risks during the first month of the Recreation and Wellness Intranet Project. However, all they did was document the risks in a list. They never ranked the risks or developed any response strategies. Because the project has had several problems, such as key team members leaving the company, users being uncooperative, and team members not providing good status information. Tony has decided to be more proactive in managing risks. He also wants to address positive risks as well as negative risks.
the quation is :
1- Plot the six risks on a probability/impact matrix.
2- assign a numeric value for the probability and impact of each risk on meeting the main project objective.
Step by step
Solved in 2 steps with 1 images