The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent.
Time (weeks)
Immediate
Time (weeks)
Immediate
Activity
b
Predecessor(s)
Activity
b
Predecessor(s)
a
a
A
10
12
C
7
10
12
A
12
16
D
6.
8
14
This exercise contains only parts a, b, c, d, and e.
a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places):
TIT
Expected
Activity
Time
Variance
A
9.83
0.69
В
11.50
3.36
9.93
0.69
8.67
1.78
b) The expected completion time of the critical path = 20.17 weeks (round your response to two decimal places).
The expected completion time of the path other than the critical path = 19.76 weeks (round your response to two decimal places).
c) The variance of the critical path = 5.14 weeks (round your response to two decimal places).
The variance of the path other than the critical path = 1.38 weeks (round your response to two decimal places).
d) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 21 weeks or less =
(enter as a probability and round your response to two decimal
places).
Transcribed Image Text:The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity b Predecessor(s) Activity b Predecessor(s) a a A 10 12 C 7 10 12 A 12 16 D 6. 8 14 This exercise contains only parts a, b, c, d, and e. a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places): TIT Expected Activity Time Variance A 9.83 0.69 В 11.50 3.36 9.93 0.69 8.67 1.78 b) The expected completion time of the critical path = 20.17 weeks (round your response to two decimal places). The expected completion time of the path other than the critical path = 19.76 weeks (round your response to two decimal places). c) The variance of the critical path = 5.14 weeks (round your response to two decimal places). The variance of the path other than the critical path = 1.38 weeks (round your response to two decimal places). d) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 21 weeks or less = (enter as a probability and round your response to two decimal places).
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Sample space, Events, and Basic Rules of Probability
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman