Smooth Chin Device Company The Smooth Chin Device Company is a manufacturer of high--end electric razors. These razors are produced using a machine--paced process. For each razor, a tray with components enters the process at the beginning of a conveyor belt. The tray then passes through the six steps (consisting of various tasks) explained in the table below. Workers perform the assembly operations on the moving tray. The last step consists of an inspection of the then fully assembled razor. The activity times of the process are as follows: Station Tasks A Preparation 1. Lay out chassis [12 sec] 2. Lay out screws [15 sec] 3. Lay out all other components [17 sec] Total time for A: 44 sec B Assembly 4. Perform task AS1 [10 sec] 5. Perform task AS2 [10 sec] 6. Perform task AS3 [20 sec] Total time for B: 40 sec C Assembly 7. Perform task AS4 [14 sec] 8. Perform task AS5 [16 sec] 9. Perform task AS6 [20 sec] 10. Perform task AS7 [5 sec] Total time for C: 55 sec D Assembly 11. Perform task AS8 [30 sec] 12. Perform task AS9 [30 sec] Total time for D: 60 sec E Assembly 13. Perform task AS10 [11 sec] 14. Perform task AS11 [19 sec] 15. Perform task AS12 [20 sec] Total time for E: 50 sec F Inspection 16. Inspect electrics [20 sec] 17. Inspect aesthetics [20 sec] Total time for F: 40 sec There are six workers, one at each of the six stations (A-F). They begin their workday at 8:00 a.m. and work steadily until 4:00 pm. (They are replaced with other workers for breaks and lunches, but the production is not slowed or stopped during these times.) Their hourly wage rate is $25 per hour. You can assume unlimited demand. What is the average labor utilization (you can ignore any start-up or empty system effects)of the six workers? Please give your answer in decimal form (e.g. 0.5 for 50% utilization).
Smooth Chin Device Company
The Smooth Chin Device Company is a manufacturer of high--end electric razors. These razors are produced using a machine--paced process. For each razor, a tray with components enters the process at the beginning of a conveyor belt. The tray then passes through the six steps (consisting of various tasks) explained in the table below. Workers perform the assembly operations on the moving tray. The last step consists of an inspection of the then fully assembled razor. The activity times of the process are as follows:
Station |
Tasks |
A Preparation |
1. Lay out chassis [12 sec] 2. Lay out screws [15 sec] 3. Lay out all other components [17 sec] Total time for A: 44 sec |
B Assembly
|
4. Perform task AS1 [10 sec] 5. Perform task AS2 [10 sec] 6. Perform task AS3 [20 sec] Total time for B: 40 sec |
C Assembly
|
7. Perform task AS4 [14 sec] 8. Perform task AS5 [16 sec] 9. Perform task AS6 [20 sec] 10. Perform task AS7 [5 sec] Total time for C: 55 sec |
D Assembly
|
11. Perform task AS8 [30 sec] 12. Perform task AS9 [30 sec] Total time for D: 60 sec |
E Assembly
|
13. Perform task AS10 [11 sec] 14. Perform task AS11 [19 sec] 15. Perform task AS12 [20 sec] Total time for E: 50 sec |
F Inspection |
16. Inspect electrics [20 sec] 17. Inspect aesthetics [20 sec] Total time for F: 40 sec
|
There are six workers, one at each of the six stations (A-F). They begin their workday at 8:00 a.m. and work steadily until 4:00 pm. (They are replaced with other workers for breaks and lunches, but the production is not slowed or stopped during these times.) Their hourly wage rate is $25 per hour. You can assume unlimited demand.
What is the average labor utilization (you can ignore any start-up or empty system effects)of the six workers? Please give your answer in decimal form (e.g. 0.5 for 50% utilization).