SITUATION 3.1 Company AAA is going to construct a 8,000 square meters cold storage factory in 6 month time steel framed and covered with the pre-painted and insulated steel roofing and wall cladding. VEST & HARD GOGGLES/ 4 PAIRS - GLOVES / SAFETY 8 PCS - DUST MASK / PERSONAL HARNESS НАТ FACE SHOES PROTECTION (1SET ONLY) (1SET ONLY) (1SET SHIELD MONTHLY EQUIPMENT (PPE) MONTHLY ONLY) 1SET ONLY Project Manager (1) 1 4 8 Project Engineer (1) 1 8 Plant Manager (1) 1. 4 1 8. Finishing (4) 1. 1. 4 Painting (4) 1. 1 Electrical (2) 1 1. 1 1 Welders (6) 1 1 4 1 Workers (100) 1 4 1 8 Safety Officer (1) 1 4. 1 8 Unit Cost ( in PhP) 465 200 300 80 1,400 20 a) How much does it cost per month without the painter and finisher? b) How much is the TOTAL BUDGET required for PPE? c) If the project is extended for another 3 months, how much is the upgraded PPE budget? d) How much does extension of construction time cost per month with finishing and painting added? e) What is the percentage increase of PPE cost over the original (6) months project duration?
SITUATION 3.1 Company AAA is going to construct a 8,000 square meters cold storage factory in 6 month time steel framed and covered with the pre-painted and insulated steel roofing and wall cladding. VEST & HARD GOGGLES/ 4 PAIRS - GLOVES / SAFETY 8 PCS - DUST MASK / PERSONAL HARNESS НАТ FACE SHOES PROTECTION (1SET ONLY) (1SET ONLY) (1SET SHIELD MONTHLY EQUIPMENT (PPE) MONTHLY ONLY) 1SET ONLY Project Manager (1) 1 4 8 Project Engineer (1) 1 8 Plant Manager (1) 1. 4 1 8. Finishing (4) 1. 1. 4 Painting (4) 1. 1 Electrical (2) 1 1. 1 1 Welders (6) 1 1 4 1 Workers (100) 1 4 1 8 Safety Officer (1) 1 4. 1 8 Unit Cost ( in PhP) 465 200 300 80 1,400 20 a) How much does it cost per month without the painter and finisher? b) How much is the TOTAL BUDGET required for PPE? c) If the project is extended for another 3 months, how much is the upgraded PPE budget? d) How much does extension of construction time cost per month with finishing and painting added? e) What is the percentage increase of PPE cost over the original (6) months project duration?
Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
Related questions
Question
Answer in letter E
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 5 steps with 2 images
Recommended textbooks for you
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education