Should the discount be accepted?
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
A company uses components at the rate of 900 units per month, which
are bought in at a cost of $3.20 each from the supplier. It costs $40 each
time to place an order, regardless of the quantity ordered. The supplier
offers a 9% discount on the purchase price for order quantities of 4,000
items or more. The current EOQ is 2,000 units. The total holding cost is
17% per annum of the value of inventory held.
Required:-
Should the discount be accepted?
Total cost-
Total cost for 2000 units-
Total cost for 4000 units-
9% is a discount on the purchase price.
Step by step
Solved in 2 steps