Sheffield Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company's controller, Landon Sheffield, based on performing 2,100 core tests per month. Standard Standard Standard Price Quantity Cost $0.50 per pound $10 per DLH $9 per DLH $16 per DLH Direct materials 5 pounds $2.50 Direct labor 0.50 DLH 5.00 Variable overhead 0.50 DLH 4.50 Fixed overhead 0.50 DLH 8.00 Total standard cost per test $20.00 At the end of March, London reported the following operational results: The company actually performed 2,280 core tests during the month. 8,500 pounds of direct materials were purchased during the month at a total cost of $5,700. 6,200 pounds of direct materials were used to conduct the core tests. 840 direct labor hours were worked at a total cost of $9,830. Actual variable overhead was $7,700. Actual fixed overhead was $15,800. (a) Calculate the direct materials price variance for March. (Round per unit value to 2 decimal places, eg. 52.75 and final answer to 0 decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter O for the amounts.) 1445 Unfavorable Direct materials price variance (b) Calculate the direct materials quantity variance for March. (Round answer to 0 decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter O for the amounts.) -2600 Favorable Direct materials quantity variance %24 %24

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Chapter 6 Question 8

Please help me with parts E,F, and G

 

Sheffield Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the
tests have been developed by the company's controller, Landon Sheffield, based on performing 2,100 core tests per month.
Standard
Standard
Standard Price
Quantity
Cost
$0.50 per pound
$10 per DLH
Direct materials
5 pounds
$2.50
Direct labor
0.50 DLH
5.00
$9 per DLH
$16 per DLH
Variable overhead
0.50 DLH
4.50
Fixed overhead
0.50 DLH
8.00
Total standard cost per test
$20.00
At the end of March, London reported the following operational results:
The company actually performed 2,280 core tests during the month.
8,500 pounds of direct materials were purchased during the month at a total cost of $5,700.
6,200 pounds of direct materials were used to conduct the core tests.
840 direct labor hours were worked at a total cost of $9,830.
Actual variable overhead was $7,700.
Actual fixed overhead was $15,800.
(a) Calculate the direct materials price variance for March. (Round per unit value to 2 decimal places, e.g. 52.75 and final answer to 0
decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter O for the amounts.)
$
Direct materials price variance
1445
Unfavorable
(b) Calculate the direct materials quantity variance for March. (Round answer to 0 decimal places, e.g. 5,275. If variance is zero, select
"Not Applicable" and enter O for the amounts.)
-2600
Favorable
Direct materials quantity variance
%24
Transcribed Image Text:Sheffield Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company's controller, Landon Sheffield, based on performing 2,100 core tests per month. Standard Standard Standard Price Quantity Cost $0.50 per pound $10 per DLH Direct materials 5 pounds $2.50 Direct labor 0.50 DLH 5.00 $9 per DLH $16 per DLH Variable overhead 0.50 DLH 4.50 Fixed overhead 0.50 DLH 8.00 Total standard cost per test $20.00 At the end of March, London reported the following operational results: The company actually performed 2,280 core tests during the month. 8,500 pounds of direct materials were purchased during the month at a total cost of $5,700. 6,200 pounds of direct materials were used to conduct the core tests. 840 direct labor hours were worked at a total cost of $9,830. Actual variable overhead was $7,700. Actual fixed overhead was $15,800. (a) Calculate the direct materials price variance for March. (Round per unit value to 2 decimal places, e.g. 52.75 and final answer to 0 decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter O for the amounts.) $ Direct materials price variance 1445 Unfavorable (b) Calculate the direct materials quantity variance for March. (Round answer to 0 decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter O for the amounts.) -2600 Favorable Direct materials quantity variance %24
(e) Calculate the variable overhead spending variance for March. (Round per unit value to 2 decimal places, eg. 52.75 and final answer to
O decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter O for the amounts.)
$
Variable overhead spending variance
(f) Calculate the variable overhead efficiency variance for March. (Round answer to O decimal places, e,g. 5,275. If variance is zero, select
"Not Applicable" and enter O for the amounts.)
$
Variable overhead efficiency variance
(g) Calculate the fixed overhead spending variance for March. (Round per unit value to 2 decimal places, eg. 52.75 and final answer to 0
decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter O for the amounts.)
Fixed overhead spending variance
%24
%24
%24
Transcribed Image Text:(e) Calculate the variable overhead spending variance for March. (Round per unit value to 2 decimal places, eg. 52.75 and final answer to O decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter O for the amounts.) $ Variable overhead spending variance (f) Calculate the variable overhead efficiency variance for March. (Round answer to O decimal places, e,g. 5,275. If variance is zero, select "Not Applicable" and enter O for the amounts.) $ Variable overhead efficiency variance (g) Calculate the fixed overhead spending variance for March. (Round per unit value to 2 decimal places, eg. 52.75 and final answer to 0 decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter O for the amounts.) Fixed overhead spending variance %24 %24 %24
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Financial Information
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education