**See Instructions For Solving @ Bottom** The contractor's construction expenses and owner's payments for a construction project are expressed in then-current inflated dollars in the table below. The monthly interest rate required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped for two months at the end of month 5 due to a labor strike while the monthly inflation rate is 0.7 percent. Under the terms of the contract between the owner and the contractor, suppose that the owner's payments will be delayed but not adjusted for inflation. Find the cumulative net cash flow with interest due to overdrafting for the following conditions: (a) if there were no labor strike and (b) when there is a strike for two months at the end of month 5. **Instructions** 1)Calculate Net Cash Flow At 2)Calculate: *Et & Et i/2 3)Calculate The Cumulative Cash Flow Before Payment = Ft with & with out interest 4)Calculate Nt = Nt-1 + It-Et + Pt 5)Calculate: It Nt i - Eti/2 6)Calculate Cumulative Net Cash Flow Nt with & with out interest *Annual Interest - It *Cumulative Cash Flow Before Payment Ft with interest *Cumulative Net Cash Flow with interest NT with interest *All Calculations For All Equations for 14 Periods Must Be Shown I Need to Verify my calculations The contractor's construction expenses and owner's payments for a construction project are expressed in then-current inflated dollars in the table below. The monthly interest rate required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped for two months at the end of month 5 due to a abor strike while the monthly inflation rate is 0.7 percent. Under the terms of the contract between the owner and the contractor, suppose that the owner's payments will be delayed but not adjusted for inflation. Find the cumulative net cash flow with interest due to overdrafting for the following conditions: (a) if there were no labor strike and (b) when there is a strike for two months at the end of month 5. End of month, t 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Total Contractor's expenses Et -$200,000 -251,250 -404,000 -527,852 -642,726 -799,734 -772,800 -683,430 -447,501 -397,442 -348,965 -270,438 -437,420 0 0 $6,183,558 Owner's Payment Pt 0 $225,000 360,000 468,000 567,000 702,000 675,000 594,000 387,000 342,000 298 230,400 370,800 1,080,000 600,000 $6,900,000

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question

Note: the answer should be typed.

 

**See Instructions For Solving @ Bottom** The contractor's construction expenses and owner's payments
for a construction project are expressed in then-current inflated dollars in the table below. The monthly
interest rate required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped for
two months at the end of month 5 due to a labor strike while the monthly inflation rate is 0.7 percent.
Under the terms of the contract between the owner and the contractor, suppose that the owner's
payments will be delayed but not adjusted for inflation. Find the cumulative net cash flow with interest due
to overdrafting for the following conditions: (a) if there were no labor strike and (b) when there is a strike
for two months at the end of month 5. **Instructions** 1) Calculate Net Cash Flow = At 2)Calculate : *Et &
Et i/2 3)Calculate The Cumulative Cash Flow Before Payment = Ft with & with out interest 4)Calculate Nt =
Nt-1 + It-Et + Pt 5) Calculate: It = Nt i - Eti/2 6)Calculate Cumulative Net Cash Flow = Nt with & with out
interest *Annual Interest - It *Cumulative Cash Flow Before Payment Ft with interest *Cumulative Net Cash
Flow with interest NT with interest *All Calculations For All Equations for 14 Periods Must Be Shown I Need
to Verify my calculations
The contractor's construction expenses and owner's payments for a construction project are
expressed in then-current inflated dollars in the table below. The monthly interest rate
required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped
for two months at the end of month 5 due to a labor strike while the monthly inflation rate
is 0.7 percent. Under the terms of the contract between the owner and the contractor,
suppose that the owner's payments will be delayed but not adjusted for inflation. Find the
cumulative net cash flow with interest due to overdrafting for the following conditions:
(a) if there were no labor strike and (b) when there is a strike for two months at the end of
month 5.
End of month, Contractor's
t
expenses Et
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Total
-$200,000
-251,250
-404,000
-527,852
-642,726
-799,734
-772,800
-683,430
-447,501
-397,442
-348,965
-270,438
-437,420
0
0
$6,183,558
Owner's
Payment Pt
0
$225,000
360,000
468,000
567,000
702,000
675,000
594,000
387,000
342,000
298,800
230,400
370,800
1,080,000
600,000
$6,900,000
Transcribed Image Text:**See Instructions For Solving @ Bottom** The contractor's construction expenses and owner's payments for a construction project are expressed in then-current inflated dollars in the table below. The monthly interest rate required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped for two months at the end of month 5 due to a labor strike while the monthly inflation rate is 0.7 percent. Under the terms of the contract between the owner and the contractor, suppose that the owner's payments will be delayed but not adjusted for inflation. Find the cumulative net cash flow with interest due to overdrafting for the following conditions: (a) if there were no labor strike and (b) when there is a strike for two months at the end of month 5. **Instructions** 1) Calculate Net Cash Flow = At 2)Calculate : *Et & Et i/2 3)Calculate The Cumulative Cash Flow Before Payment = Ft with & with out interest 4)Calculate Nt = Nt-1 + It-Et + Pt 5) Calculate: It = Nt i - Eti/2 6)Calculate Cumulative Net Cash Flow = Nt with & with out interest *Annual Interest - It *Cumulative Cash Flow Before Payment Ft with interest *Cumulative Net Cash Flow with interest NT with interest *All Calculations For All Equations for 14 Periods Must Be Shown I Need to Verify my calculations The contractor's construction expenses and owner's payments for a construction project are expressed in then-current inflated dollars in the table below. The monthly interest rate required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped for two months at the end of month 5 due to a labor strike while the monthly inflation rate is 0.7 percent. Under the terms of the contract between the owner and the contractor, suppose that the owner's payments will be delayed but not adjusted for inflation. Find the cumulative net cash flow with interest due to overdrafting for the following conditions: (a) if there were no labor strike and (b) when there is a strike for two months at the end of month 5. End of month, Contractor's t expenses Et 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Total -$200,000 -251,250 -404,000 -527,852 -642,726 -799,734 -772,800 -683,430 -447,501 -397,442 -348,965 -270,438 -437,420 0 0 $6,183,558 Owner's Payment Pt 0 $225,000 360,000 468,000 567,000 702,000 675,000 594,000 387,000 342,000 298,800 230,400 370,800 1,080,000 600,000 $6,900,000
Expert Solution
steps

Step by step

Solved in 5 steps with 38 images

Blurred answer
Knowledge Booster
Inflation and Unemployment
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education