scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a 'Hehsite': Activity Description Duration (days) Preceding Activities Determine user needs Review s/w and languages Purchase software 5 D. Design format and style Write programs Review outcome product with user Make revisions H. Select server site E Install on server D. F Test G, H, I 1. Draw the path. 2. Calculate the carly finishing time (forwards calculations) 3. Highlight the total time to complete the project (days or weeks) 4. Calculate the late finishing time (backwards calculations) 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path (highlight critical path activities) 7. what would happen if revised to take seven weeks instead of five weeks

Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
icon
Related questions
Question
scenarios of a project activities (tables given below) and their required times to be completed in
addition to their predecessors for developing a 'Hehsite':
Activity
Description
Duration (days)
Preceding Activities
Determine user needs
Review s/w and languages
Purchase software
5
D.
Design format and style
Write programs
Review outcome product with user
Make revisions
H.
Select server site
E
Install on server
D. F
Test
G, H, I
1. Draw the path.
2. Calculate the carly finishing time (forwards calculations)
3. Highlight the total time to complete the project (days or weeks)
4. Calculate the late finishing time (backwards calculations)
5. Calculate the slack time of the non-critical path activities
6. Identify the critical path (highlight critical path activities)
7. what would happen if revised to take seven weeks instead of five weeks
Transcribed Image Text:scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a 'Hehsite': Activity Description Duration (days) Preceding Activities Determine user needs Review s/w and languages Purchase software 5 D. Design format and style Write programs Review outcome product with user Make revisions H. Select server site E Install on server D. F Test G, H, I 1. Draw the path. 2. Calculate the carly finishing time (forwards calculations) 3. Highlight the total time to complete the project (days or weeks) 4. Calculate the late finishing time (backwards calculations) 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path (highlight critical path activities) 7. what would happen if revised to take seven weeks instead of five weeks
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Database System Concepts
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
C How to Program (8th Edition)
C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON
Database Systems: Design, Implementation, & Manag…
Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning
Programmable Logic Controllers
Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education