Salinger Company estimates that total factory overhead costs will be $78,000 for the year. Direct labor hours are estimated to be 13,000. a. For Salinger Company, determine the predetermined factory overhead rate using direct labor hours as the activity base. If required, round your answer to two decimal places b. During August, Salinger Company accumulated 850 hours of direct labor costs on Job 40 and 530 hours on Job 42. Determine the amount of factory overhead applied to Jobs 40 and 42 in August. c. Prepare the journal entry to apply factory overhead to both jobs in August according to the predetermined overhead rate.
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
Salinger Company estimates that total
a. For Salinger Company, determine the predetermined factory overhead rate using direct labor hours as the activity base. If required, round your answer to two decimal places
b. During August, Salinger Company accumulated 850 hours of direct labor costs on Job 40 and 530 hours on Job 42. Determine the amount of factory overhead applied to Jobs 40 and 42 in August.
c. Prepare the