s the Manager of Branson’s Department Store, you are responsible for ensuring that reorder quantities for the various items have been correctly established. You decide to test one item and choose product Z. A continuous review inventory policy has been used, so you examine this as well as other records and come up with the following data: Cost per unit $35 Holding cost 20 percent of unit cost Average daily demand 10 units Ordering cost $30 per order Standard deviation of daily demand 3 units Delivery lead time 4 days
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
As the Manager of Branson’s Department Store, you are responsible for ensuring that reorder quantities for the various items have been correctly established. You decide to test one item and choose product Z. A continuous review inventory policy has been used, so you examine this as well as other records and come up with the following data:
Cost per unit |
$35 |
Holding cost |
20 percent of unit cost |
Average daily demand |
10 units |
Ordering cost |
$30 per order |
Standard deviation of daily demand |
3 units |
Delivery lead time |
4 days |
Because customers generally do not wait but go elsewhere, you decide on a service probability of 90 percent. Assume that Branson’s Department Store operates 320 days per year.
- [What is the annual demand (D)?
- Determine the optimal order quantity, Q*.
- Determine the reorder point (R) if demand is constant.
- Determine the reorder point (R) if demand is varies.
Step by step
Solved in 5 steps with 1 images