Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic. Room Room Room 1 2 Room 5 3 Room Room 6 His foreman has completed a month-long study of the number of loads of material that have moved from one process to another in the current building. This information is contained in the flow matrix on the left below. Finally, Creasey also developed a matrix to indicate distances between the work areas shown in the building schematic, shown on the right below. 1 2 3 4 5 6 From To Materials Welding Drills Lathes Grinders Benders Materials 1 20 40 20 40 60 100 50 0 50 20 40 20 40 Welding Drills 25 50 3 60 40 20 25 50 - 20 40 Lathes 25 20 20 Grinders 50 100 6 Benders 10 20 Based on the flows shown in the matrix, it is likely that the processes Drills and are in rooms next to each other as they have the highest number of moves between each other. Based on the flows shown in the matrix, it is likely that the processes Materials and are in rooms next to each other as they have the second highest number of moves between each other. One of the layouts that could be designed is: Room 1 = Benders Room 2 = Materials Room 3 = Welding Room 4 = Drills Room 5 = Grinders Room 6 = Lathes The cumulative distance based on the overall movement of material between processes for this layout = feet (enter your response as a whole number). %3D

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Lay

Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about
safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic.
Room
Room
Room
1
2
3
Room
Room
Room
5
6
His foreman has completed a month-long study of the number of loads of material that have moved from one process to another in the current building. This information is contained in the flow matrix on the left below. Finally, Creasey also developed a matrix
to indicate distances between the work areas shown in the building schematic, shown on the right below.
From To Materials Welding Drills Lathes Grinders Benders
1 2
3
4
6
1
20 40 20 40 60
Materials
100
50
50
2
20 40 20 40
Welding
25
50
3
60 40 20
Drills
25
50
4
20 40
Lathes
25
20
20
Grinders
50
100
Benders
10
20
Based on the flows shown in the matrix, it is likely that the processes Drills and
V are in rooms next to each other as they have the highest number of moves between each other.
Based on the flows shown in the matrix, it is likely that the processes Materials and
are in rooms next to each other as they have the second highest number of moves between each other.
One of the layouts that could be designed is:
Room 1 = Benders
Room 4 = Drills
Room 2 = Materials
Room 5 = Grinders
Room 3 = Welding
Room 6 = Lathes
The cumulative distance based on the overall movement of material between processes for this layout =
feet (enter your response as a whole number).
Transcribed Image Text:Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic. Room Room Room 1 2 3 Room Room Room 5 6 His foreman has completed a month-long study of the number of loads of material that have moved from one process to another in the current building. This information is contained in the flow matrix on the left below. Finally, Creasey also developed a matrix to indicate distances between the work areas shown in the building schematic, shown on the right below. From To Materials Welding Drills Lathes Grinders Benders 1 2 3 4 6 1 20 40 20 40 60 Materials 100 50 50 2 20 40 20 40 Welding 25 50 3 60 40 20 Drills 25 50 4 20 40 Lathes 25 20 20 Grinders 50 100 Benders 10 20 Based on the flows shown in the matrix, it is likely that the processes Drills and V are in rooms next to each other as they have the highest number of moves between each other. Based on the flows shown in the matrix, it is likely that the processes Materials and are in rooms next to each other as they have the second highest number of moves between each other. One of the layouts that could be designed is: Room 1 = Benders Room 4 = Drills Room 2 = Materials Room 5 = Grinders Room 3 = Welding Room 6 = Lathes The cumulative distance based on the overall movement of material between processes for this layout = feet (enter your response as a whole number).
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.