Roscoe Construction Company (RCC) is a company specializing in building roads and highways. As a part of its business, it receives supplies of aggregate from two suppliers: Toorak Gravel (TG) and Kilda Corporation (KC). RCC purchasing has expressed a preference for KC based on price, but occasionally has to order from TG when KC cannot fill the order. RCC has recently had problems with the quality and the timeliness of deliveries. When a supplier delivers a load to RCC, it goes through an initial inspection to assure it meets specification. If the load fails the initial inspection, it goes through a secondary inspection to determine the exact issue. Almost always, the issue can be resolved and the load can be used. The initial inspection costs $2,496 per load. A secondary inspection, which is more thorough, costs $6,275 per load. If a delivery is delayed, RCC has to hire temporary workers or pay overtime to some employees. The average cost of a delayed load is $3,275. The following are summary statistics from last year's purchases from the two suppliers. Toorak Gravel Kilda Corp. Number of loads. Average tons per load 100 10,000 400 5,000 Average price per ton $ 6.00 Number of initial inspections passed Number of delayed deliveries 94 10 $ 5.90 300 80 Required: Calculate the effective cost of a ton of aggregate from the two suppliers, assuming that last year's experience is representative. (Round "Average price paid per ton" & "Average effective price per ton" answers to 2 decimal places.) Answer is complete but not entirely correct. Item Loads purchased Toorak Gravel Kilda Corporation 100 400 Average tons per load Total tons purchased Loads passing initial inspection 10,000 5,000 1,000,000 2,000,000 94 300 Loads delayed 10 80 Average price paid per ton $ 6.00 $ 5.90 Total purchase price $ 6,000,000 Initial inspection costs Secondary inspection costs Delay costs Total costs $240,800 $ 37,200 $ 32,000 $ 11,800,000 $ 963,200 $620,000 $256,000 × $ 6,310,000 $ 13,639,200 Average effective price per ton $ 6.31 $ 6.82x

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter16: Cost-volume-profit Analysis
Section: Chapter Questions
Problem 38P
icon
Related questions
Question

Rahul 

Roscoe Construction Company (RCC) is a company specializing in building roads and highways. As a part of its business, it receives
supplies of aggregate from two suppliers: Toorak Gravel (TG) and Kilda Corporation (KC). RCC purchasing has expressed a preference
for KC based on price, but occasionally has to order from TG when KC cannot fill the order.
RCC has recently had problems with the quality and the timeliness of deliveries. When a supplier delivers a load to RCC, it goes
through an initial inspection to assure it meets specification. If the load fails the initial inspection, it goes through a secondary
inspection to determine the exact issue. Almost always, the issue can be resolved and the load can be used. The initial inspection
costs $2,496 per load. A secondary inspection, which is more thorough, costs $6,275 per load. If a delivery is delayed, RCC has to hire
temporary workers or pay overtime to some employees. The average cost of a delayed load is $3,275.
The following are summary statistics from last year's purchases from the two suppliers.
Toorak
Gravel
Kilda
Corp.
Number of loads.
Average tons per load
100
10,000
400
5,000
Average price per ton
$ 6.00
Number of initial inspections passed
Number of delayed deliveries
94
10
$ 5.90
300
80
Required:
Calculate the effective cost of a ton of aggregate from the two suppliers, assuming that last year's experience is representative.
(Round "Average price paid per ton" & "Average effective price per ton" answers to 2 decimal places.)
Answer is complete but not entirely correct.
Item
Loads purchased
Toorak
Gravel
Kilda
Corporation
100
400
Average tons per load
Total tons purchased
Loads passing initial inspection
10,000
5,000
1,000,000
2,000,000
94
300
Loads delayed
10
80
Average price paid per ton
$
6.00
$
5.90
Total purchase price
$ 6,000,000
Initial inspection costs
Secondary inspection costs
Delay costs
Total costs
$240,800
$ 37,200
$ 32,000
$ 11,800,000
$ 963,200
$620,000
$256,000 ×
$ 6,310,000
$ 13,639,200
Average effective price per ton
$
6.31
$
6.82x
Transcribed Image Text:Roscoe Construction Company (RCC) is a company specializing in building roads and highways. As a part of its business, it receives supplies of aggregate from two suppliers: Toorak Gravel (TG) and Kilda Corporation (KC). RCC purchasing has expressed a preference for KC based on price, but occasionally has to order from TG when KC cannot fill the order. RCC has recently had problems with the quality and the timeliness of deliveries. When a supplier delivers a load to RCC, it goes through an initial inspection to assure it meets specification. If the load fails the initial inspection, it goes through a secondary inspection to determine the exact issue. Almost always, the issue can be resolved and the load can be used. The initial inspection costs $2,496 per load. A secondary inspection, which is more thorough, costs $6,275 per load. If a delivery is delayed, RCC has to hire temporary workers or pay overtime to some employees. The average cost of a delayed load is $3,275. The following are summary statistics from last year's purchases from the two suppliers. Toorak Gravel Kilda Corp. Number of loads. Average tons per load 100 10,000 400 5,000 Average price per ton $ 6.00 Number of initial inspections passed Number of delayed deliveries 94 10 $ 5.90 300 80 Required: Calculate the effective cost of a ton of aggregate from the two suppliers, assuming that last year's experience is representative. (Round "Average price paid per ton" & "Average effective price per ton" answers to 2 decimal places.) Answer is complete but not entirely correct. Item Loads purchased Toorak Gravel Kilda Corporation 100 400 Average tons per load Total tons purchased Loads passing initial inspection 10,000 5,000 1,000,000 2,000,000 94 300 Loads delayed 10 80 Average price paid per ton $ 6.00 $ 5.90 Total purchase price $ 6,000,000 Initial inspection costs Secondary inspection costs Delay costs Total costs $240,800 $ 37,200 $ 32,000 $ 11,800,000 $ 963,200 $620,000 $256,000 × $ 6,310,000 $ 13,639,200 Average effective price per ton $ 6.31 $ 6.82x
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning