Road Gripper Tire Co. manufactures automobile tires. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 4,160 tires were as follows:

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
icon
Concept explainers
Topic Video
Question

May you help me with this please

r
Obj. 3, 4
Road Gripper Tire Co. manufactures automobile tires. Standard costs and actual
costs for direct materials, direct labor, and factory overhead incurred for the
manufacture of 4,160 tires were as follows:
Direct materials
Direct labor
Factory overhead
Standard Costs
100,000 lb. at $6.40
2,080 hrs. at $15.75
Rates per direct labor hr.,
based on 100% of normal
capacity of 2,000 direct
labor hrs.:
Variable cost, $4.00
Fixed cost, $6.00
Each tire requires 0.5 hour of direct labor.
Actual Costs
101,000 lb. at $6.50
2,000 hrs. at $15.40
$8,200 variable cost
$12,000 fixed cost
Excel
Transcribed Image Text:r Obj. 3, 4 Road Gripper Tire Co. manufactures automobile tires. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 4,160 tires were as follows: Direct materials Direct labor Factory overhead Standard Costs 100,000 lb. at $6.40 2,080 hrs. at $15.75 Rates per direct labor hr., based on 100% of normal capacity of 2,000 direct labor hrs.: Variable cost, $4.00 Fixed cost, $6.00 Each tire requires 0.5 hour of direct labor. Actual Costs 101,000 lb. at $6.50 2,000 hrs. at $15.40 $8,200 variable cost $12,000 fixed cost Excel
40
49
B
66
67
68
50
51 Variable factory overhead controllable variance:
52 Actual variable FO cost incurred
53
54
55
69
70
71
72
D
56 Fixed factory overhead volume variance:
57
58
59
60
61
62
63 Total factory overhead cost variance
64
65
Budgeted variable FO cost for 2,080 hrs.
Variance
>
Hours at normal capacity
Standard hours for amount produced
Productive capacity not used
Standard fixed FO cost rate
Variance
Pr. 23-3B
Factory Overhead Cost Variance
E
+
F
G
H
I
J
LM
KL
N
O
Actual Factory
Overhead
P
Alternative Computation of Overhead Variances:
Actual costs
Balance
Controllable
Variance
⠀
QR S TU
V
Factory Overhead
Variable cost
Fixed cost
Total
W
Total Factory
Overhead Cost
Variance
Budgeted Factory Overhead
for Amount Produced
X YZ
Applied costs
AA
Volume
Variance
AIAC
AD ΑΔ
Applied Factory
Overhead
Transcribed Image Text:40 49 B 66 67 68 50 51 Variable factory overhead controllable variance: 52 Actual variable FO cost incurred 53 54 55 69 70 71 72 D 56 Fixed factory overhead volume variance: 57 58 59 60 61 62 63 Total factory overhead cost variance 64 65 Budgeted variable FO cost for 2,080 hrs. Variance > Hours at normal capacity Standard hours for amount produced Productive capacity not used Standard fixed FO cost rate Variance Pr. 23-3B Factory Overhead Cost Variance E + F G H I J LM KL N O Actual Factory Overhead P Alternative Computation of Overhead Variances: Actual costs Balance Controllable Variance ⠀ QR S TU V Factory Overhead Variable cost Fixed cost Total W Total Factory Overhead Cost Variance Budgeted Factory Overhead for Amount Produced X YZ Applied costs AA Volume Variance AIAC AD ΑΔ Applied Factory Overhead
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education