Rhett Corporation provides the following information for 2020: 20 Budgeted manufacturing overhead costs $1,200,000 Budgeted direct manufacturing labor-hours 20,000 hours Actual manufacturing overhead costs $1,250,000 Actual direct manufacturing labor-hours 25,000 hours 1.200100 201000 The following information for a job at 40 Philadelphia Company: Actual direct materials costs $ 6,000 Actual direct manufacturing labor 200 hours Actual direct manufacturing labor rate $ 56 per hour 7) Calculate the total manufacturing costs of a job at 40 Philadelphia Company using actual costir 8) Calculate the total manufacturing costs of a job at 40 Philadelphia
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Rhett Corporation provides the following information for 2020:
20
Budgeted
Actual manufacturing overhead costs $1,250,000
Actual direct manufacturing labor-hours 25,000 hours
1.200100 201000
The following information for a job at 40 Philadelphia Company:
Actual direct materials costs $ 6,000 Actual direct manufacturing labor 200 hours
Actual direct manufacturing labor rate $ 56 per hour
7) Calculate the total manufacturing costs of a job at 40 Philadelphia Company using actual costir 8) Calculate the total manufacturing costs of a job at 40 Philadelphia Company using normal costa


Step by step
Solved in 2 steps