Question
CASE 3
On January 1, 20x1, Qwerty, Inc. entered into a construction contract with an owner to build an oil refinery.
The oil refinery is highly customized to the owner's specifications, and changes to these specifications by the
owner are expected over the contract term. The oil refinery does not have an alternative use to the contractor.
Nonrefundable, interim progress payments are required as a mechanism to finance the contract. The owner
can cancel the contract at any time (with a termination penalty); any work in process is the property of the
owner. As a result, another entity would not need to reperform the tasks performed to date. Physical
possession and title do not pass until completion of the contract. The contractor determines that the contract
has a single performance obligation to build the refinery. The preponderance of evidence suggests that the
contractor's performance creates an asset that the customer controls and control are being transferred over
time. Qwerty, Inc. concludes that input method is a more reasonable method for measuring the progress
toward satisfying its performance obligation.
The contract duration is three (3) years with total estimated contract revenue of P30,000,000. The total
estimated contract cost as of December 31, 20x1 is P20,000,000. The cost incurred during 20x1 is
P12,000,000, including P2,000,000 related to contractor-caused inefficiencies which do not represent the
transfer of goods or services to the customer. As of December 31, 20x2, the total estimated contract cost
becomes P25,000,000 due to an increase in cost of raw materials. The cost incurred during 20x2 is
P10,500,000 including P500,000 related to contractor-caused inefficiencies, which do not represent transfer of
goods or services to the customer.
REQUIRED: Under IFRS 15, determine the following:
7. Percentage of completion for 20x2
8. Realized gross profit (loss) for 20x1
9. Realized gross profit (loss) for 20x2
10. Net income (loss) for the year ended Dec. 31, 20x2
Transcribed Image Text:CASE 3 On January 1, 20x1, Qwerty, Inc. entered into a construction contract with an owner to build an oil refinery. The oil refinery is highly customized to the owner's specifications, and changes to these specifications by the owner are expected over the contract term. The oil refinery does not have an alternative use to the contractor. Nonrefundable, interim progress payments are required as a mechanism to finance the contract. The owner can cancel the contract at any time (with a termination penalty); any work in process is the property of the owner. As a result, another entity would not need to reperform the tasks performed to date. Physical possession and title do not pass until completion of the contract. The contractor determines that the contract has a single performance obligation to build the refinery. The preponderance of evidence suggests that the contractor's performance creates an asset that the customer controls and control are being transferred over time. Qwerty, Inc. concludes that input method is a more reasonable method for measuring the progress toward satisfying its performance obligation. The contract duration is three (3) years with total estimated contract revenue of P30,000,000. The total estimated contract cost as of December 31, 20x1 is P20,000,000. The cost incurred during 20x1 is P12,000,000, including P2,000,000 related to contractor-caused inefficiencies which do not represent the transfer of goods or services to the customer. As of December 31, 20x2, the total estimated contract cost becomes P25,000,000 due to an increase in cost of raw materials. The cost incurred during 20x2 is P10,500,000 including P500,000 related to contractor-caused inefficiencies, which do not represent transfer of goods or services to the customer. REQUIRED: Under IFRS 15, determine the following: 7. Percentage of completion for 20x2 8. Realized gross profit (loss) for 20x1 9. Realized gross profit (loss) for 20x2 10. Net income (loss) for the year ended Dec. 31, 20x2
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Financial Statements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education