Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9) [The following information applies to the questions displayed below) In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 $2,059,000 5,041,000 2,190,000 1,895,000 2025 $2,627,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. 2,414,000 2,496,000 2,400,000 2026 $2,655,400 5,314,000 5,705,000 Problem 6-10 (Algo) Part 2 2-a. in the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc. for construction costs incurred) 2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs incurred) 2-c. In the journal below, complete the necessary journal entries for the year 2026 (credit "Cash, Materials, etc." for construction costs incurred)

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Please do not give solution in image format ?.

Reg 28
Reg 20
In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs
incurred).
Note: If no entry is required for a transaction/event, select "No journal entry required in the first account field.
Reg 2A
View transaction list
Journal entry worksheet
Record construction costs.
Note: Enter debits before credits
Date
2024
Record entry
General Journal
Clear entry
ⒸHA
Debit
Credit
View general journal
Req 28 >
Transcribed Image Text:Reg 28 Reg 20 In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). Note: If no entry is required for a transaction/event, select "No journal entry required in the first account field. Reg 2A View transaction list Journal entry worksheet Record construction costs. Note: Enter debits before credits Date 2024 Record entry General Journal Clear entry ⒸHA Debit Credit View general journal Req 28 >
w
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9)
[The following information applies to the questions displayed below)
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
2024
$2,059,000
5,041,000
2,190,000
1,895,000
Complete this question by entering your answers in the tabs below.
Reg 2A
Problem 6-10 (Algo) Part 2
2-a, in the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc. for construction costs
incurred)
2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc. for construction costs
incurred)
2-c. In the journal below, complete the necessary journal entries for the year 2026 (credit "Cash, Materials, etc." for construction costs
incurred)
Reg 28
2025
$2,627,000
2,414,000
2,496,000
2,400,000
Reg 2C
2026
$2,655,400
5,314,000
5,705,000
In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs
incurred).
Note: If no entry is required for a transaction/event, select "No journal entry required in the first account field.
View transaction fiat
Transcribed Image Text:w Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9) [The following information applies to the questions displayed below) In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. 2024 $2,059,000 5,041,000 2,190,000 1,895,000 Complete this question by entering your answers in the tabs below. Reg 2A Problem 6-10 (Algo) Part 2 2-a, in the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc. for construction costs incurred) 2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc. for construction costs incurred) 2-c. In the journal below, complete the necessary journal entries for the year 2026 (credit "Cash, Materials, etc." for construction costs incurred) Reg 28 2025 $2,627,000 2,414,000 2,496,000 2,400,000 Reg 2C 2026 $2,655,400 5,314,000 5,705,000 In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). Note: If no entry is required for a transaction/event, select "No journal entry required in the first account field. View transaction fiat
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Accounting for Intangible assets
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education