Required: 01. The predetermined overhead rate under the traditional costing system is closest to: 02. The overhead cost per unit of Product A under the traditional costing system is closest to: 03. The predetermined overhead rate (i.e., activity rate) for Activity 1 under the activity-based costing system is closest to:
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
Acklin Company has two products: A and B. The annual production and sales of Product A is 600 units and of Product B is 900 units. The company has traditionally used direct labor-hours as the basis for applying all manufacturing
The company is considering switching to an activity-based costing system for the purpose of computing unit product costs for external reports. The new activitybased costing system would have three overhead activity cost pools--Activity 1, Activity 2, and General Factory--with estimated overhead costs and expected activity as follows:
Estimated
Overhead
Activity Cost pool Costs Expected Activity
Product A Product B Total
Activity 1 $18,900 700 200 900
Activity 2 $15,631 1,000 100 1,100
General Factory $28,791 300 270 570
Total $63,322
(Note: The General
labor-hours.)
Required:
01. The predetermined overhead rate under the traditional costing system is closest to:
02. The overhead cost per unit of Product A under the traditional costing system is closest to:
03. The predetermined overhead rate (i.e., activity rate) for Activity 1 under the activity-based costing system is closest to:
04. The overhead cost per unit of Product A under the activity-based costing system is closest to.