Refer to a table below. What is the cumulative budgeted cost at the end of week 6?  Below is the table of actual costs. What is the cumulative actual cost at the end of week 6?  Below is the table for cumulative percentages of work completed by the end of week 6. What is the cumulative earned value of the project at the end of week 6?

Quickbooks Online Accounting
3rd Edition
ISBN:9780357391693
Author:Owen
Publisher:Owen
Chapter8: Budgets And Bank Reconciliations
Section: Chapter Questions
Problem 3.6C
icon
Related questions
icon
Concept explainers
Question

Kindly refer to the attached photo in answering the questions: Thank you!☺️

 

  1. Refer to a table below. What is the cumulative budgeted cost at the end of week 6? 
  2. Below is the table of actual costs. What is the cumulative actual cost at the end of week 6? 
  3. Below is the table for cumulative percentages of work completed by the end of week 6. What is the cumulative earned value of the project at the end of week 6? 
  4. What is the CPI at the end of week 6? (round up to 2 decimal place)
  5. What is the value of CV?
  6. Calculate the FCAC using the first two methods described in the chapter.
  7. Compute for the TCPI. 

Answer first the problem solving before start answering the final exam. There are questions that will be taken from the problem.
Refer to a table below. What is the cumulative budgeted cost at the end of week 6?
>
Week
TBC
2
3
4
5
6
7
8
9
10
Task 1
30
10
15
Task 2
70
10
10
10
20
10
10
Task 3
40
5
25
Task 4
30
5
5
20
Total
170
10
25
15
10
25
15
35
10
20
Cumulative
Below is the table of actual costs. What is the cumulative actual cost at the end of week 6?
Week
1
2
3
4
6
Task 1
10
16
8.
Task 2
10
10
12
24
12
Task 3
Task 4
Total
10
26
18
12
29
17
Cumulative
Below is the table for cumulative percentages of work completed by the end of week 6. What is the cumulative earned value of the project at the end
of week 6?
Week
1
3
5
6
Task 1
30
80
100
100
100
100
Task 2
10
25
35
55
65
Task 3
10
20
Task 4
Total
Cumulative
What is the CPl at the end of week 6? (round up to 2 decimal place)
What is the value of CV?
Calculate the FCAC using the first two methods described in the chapter.
Compute for the TCPI.
Transcribed Image Text:Answer first the problem solving before start answering the final exam. There are questions that will be taken from the problem. Refer to a table below. What is the cumulative budgeted cost at the end of week 6? > Week TBC 2 3 4 5 6 7 8 9 10 Task 1 30 10 15 Task 2 70 10 10 10 20 10 10 Task 3 40 5 25 Task 4 30 5 5 20 Total 170 10 25 15 10 25 15 35 10 20 Cumulative Below is the table of actual costs. What is the cumulative actual cost at the end of week 6? Week 1 2 3 4 6 Task 1 10 16 8. Task 2 10 10 12 24 12 Task 3 Task 4 Total 10 26 18 12 29 17 Cumulative Below is the table for cumulative percentages of work completed by the end of week 6. What is the cumulative earned value of the project at the end of week 6? Week 1 3 5 6 Task 1 30 80 100 100 100 100 Task 2 10 25 35 55 65 Task 3 10 20 Task 4 Total Cumulative What is the CPl at the end of week 6? (round up to 2 decimal place) What is the value of CV? Calculate the FCAC using the first two methods described in the chapter. Compute for the TCPI.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Quickbooks Online Accounting
Quickbooks Online Accounting
Accounting
ISBN:
9780357391693
Author:
Owen
Publisher:
Cengage