Refer to a table below. What is the cumulative budgeted cost at the end of week 6? Below is the table of actual costs. What is the cumulative actual cost at the end of week 6? Below is the table for cumulative percentages of work completed by the end of week 6. What is the cumulative earned value of the project at the end of week 6?
Master Budget
A master budget can be defined as an estimation of the revenue earned or expenses incurred over a specified period of time in the future and it is generally prepared on a periodic basis which can be either monthly, quarterly, half-yearly, or annually. It helps a business, an organization, or even an individual to manage the money effectively. A budget also helps in monitoring the performance of the people in the organization and helps in better decision-making.
Sales Budget and Selling
A budget is a financial plan designed by an undertaking for a definite period in future which acts as a major contributor towards enhancing the financial success of the business undertaking. The budget generally takes into account both current and future income and expenses.
Kindly refer to the attached photo in answering the questions: Thank you!☺️
- Refer to a table below. What is the cumulative budgeted cost at the end of week 6?
- Below is the table of actual costs. What is the cumulative actual cost at the end of week 6?
- Below is the table for cumulative percentages of work completed by the end of week 6. What is the cumulative earned value of the project at the end of week 6?
- What is the CPI at the end of week 6? (round up to 2 decimal place)
- What is the value of CV?
- Calculate the FCAC using the first two methods described in the chapter.
- Compute for the TCPI.