[Questions 12-13] Suppose that a manager is given a new project with the following cash flows: Cash flow ($ million) -100 30 40 50 50 Year O 1 2 3 4 What is the internal rate of return of this project? According to the IRR rule, should the manager undertake this project? O IRR is 15.3%. The manager needs to undertake this project because the IRR is higher than the discount rate. O IRR is 15.3%. The manager should not undertake this project because the IRR is higher than the discount rate. IRR is 22.8%. The manager needs to undertake this project because the IRR is higher than the discount rate. IRR is 22.8%. The manager should not undertake this project because the IRR is higher than the discount rate.

Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
icon
Related questions
icon
Concept explainers
Topic Video
Question
[Questions 12-13] Suppose that a manager is given a new project with the following cash flows:
Cash flow ($ million)
-100
30
40
50
50
Year
0
1
2
3
4
What is the internal rate of return of this project? According to the IRR rule, should the manager
undertake this project?
IRR is 15.3%. The manager needs to undertake this project because the IRR is higher than the discount rate.
IRR is 15.3%. The manager should not undertake this project because the IRR is higher than the discount rate.
IRR is 22.8%. The manager needs to undertake this project because the IRR is higher than the discount rate.
IRR is 22.8%. The manager should not undertake this project because the IRR is higher than the discount rate.
Transcribed Image Text:[Questions 12-13] Suppose that a manager is given a new project with the following cash flows: Cash flow ($ million) -100 30 40 50 50 Year 0 1 2 3 4 What is the internal rate of return of this project? According to the IRR rule, should the manager undertake this project? IRR is 15.3%. The manager needs to undertake this project because the IRR is higher than the discount rate. IRR is 15.3%. The manager should not undertake this project because the IRR is higher than the discount rate. IRR is 22.8%. The manager needs to undertake this project because the IRR is higher than the discount rate. IRR is 22.8%. The manager should not undertake this project because the IRR is higher than the discount rate.
[Questions 12-13] Suppose that a manager is given a new project with the following cash flows:
Cash flow ($ million)
-100
30
40
50
50
Year
1
2
3
4
The project discount rate is 8%. What is the NPV of the project? According to the NPV rule, should the
manager undertake this project?
NPV is $38.51 million. According to the NPV rule, the manager needs to undertake this project.
NPV is $38.51 million. According to the NPV rule, the manager should not undertake this project and had better wait for another
project with a higher NPV.
NPV is $70.00 million. According to the NPV rule, the manager needs to undertake this project.
NPV is $70.00 million. According to the NPV rule, the manager should not undertake this project and had better wait for another
project with a higher NPV.
Transcribed Image Text:[Questions 12-13] Suppose that a manager is given a new project with the following cash flows: Cash flow ($ million) -100 30 40 50 50 Year 1 2 3 4 The project discount rate is 8%. What is the NPV of the project? According to the NPV rule, should the manager undertake this project? NPV is $38.51 million. According to the NPV rule, the manager needs to undertake this project. NPV is $38.51 million. According to the NPV rule, the manager should not undertake this project and had better wait for another project with a higher NPV. NPV is $70.00 million. According to the NPV rule, the manager needs to undertake this project. NPV is $70.00 million. According to the NPV rule, the manager should not undertake this project and had better wait for another project with a higher NPV.
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Essentials Of Investments
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
FUNDAMENTALS OF CORPORATE FINANCE
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:
9781260013962
Author:
BREALEY
Publisher:
RENT MCG
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
Foundations Of Finance
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education