[Questions 12-13] Suppose that a manager is given a new project with the following cash flows: Cash flow ($ million) -100 30 40 50 50 Year O 1 2 3 4 What is the internal rate of return of this project? According to the IRR rule, should the manager undertake this project? O IRR is 15.3%. The manager needs to undertake this project because the IRR is higher than the discount rate. O IRR is 15.3%. The manager should not undertake this project because the IRR is higher than the discount rate. IRR is 22.8%. The manager needs to undertake this project because the IRR is higher than the discount rate. IRR is 22.8%. The manager should not undertake this project because the IRR is higher than the discount rate.

Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
icon
Related questions
icon
Concept explainers
Topic Video
Question
[Questions 12-13] Suppose that a manager is given a new project with the following cash flows:
Cash flow ($ million)
-100
30
40
50
50
Year
0
1
2
3
4
What is the internal rate of return of this project? According to the IRR rule, should the manager
undertake this project?
IRR is 15.3%. The manager needs to undertake this project because the IRR is higher than the discount rate.
IRR is 15.3%. The manager should not undertake this project because the IRR is higher than the discount rate.
IRR is 22.8%. The manager needs to undertake this project because the IRR is higher than the discount rate.
IRR is 22.8%. The manager should not undertake this project because the IRR is higher than the discount rate.
Transcribed Image Text:[Questions 12-13] Suppose that a manager is given a new project with the following cash flows: Cash flow ($ million) -100 30 40 50 50 Year 0 1 2 3 4 What is the internal rate of return of this project? According to the IRR rule, should the manager undertake this project? IRR is 15.3%. The manager needs to undertake this project because the IRR is higher than the discount rate. IRR is 15.3%. The manager should not undertake this project because the IRR is higher than the discount rate. IRR is 22.8%. The manager needs to undertake this project because the IRR is higher than the discount rate. IRR is 22.8%. The manager should not undertake this project because the IRR is higher than the discount rate.
[Questions 12-13] Suppose that a manager is given a new project with the following cash flows:
Cash flow ($ million)
-100
30
40
50
50
Year
1
2
3
4
The project discount rate is 8%. What is the NPV of the project? According to the NPV rule, should the
manager undertake this project?
NPV is $38.51 million. According to the NPV rule, the manager needs to undertake this project.
NPV is $38.51 million. According to the NPV rule, the manager should not undertake this project and had better wait for another
project with a higher NPV.
NPV is $70.00 million. According to the NPV rule, the manager needs to undertake this project.
NPV is $70.00 million. According to the NPV rule, the manager should not undertake this project and had better wait for another
project with a higher NPV.
Transcribed Image Text:[Questions 12-13] Suppose that a manager is given a new project with the following cash flows: Cash flow ($ million) -100 30 40 50 50 Year 1 2 3 4 The project discount rate is 8%. What is the NPV of the project? According to the NPV rule, should the manager undertake this project? NPV is $38.51 million. According to the NPV rule, the manager needs to undertake this project. NPV is $38.51 million. According to the NPV rule, the manager should not undertake this project and had better wait for another project with a higher NPV. NPV is $70.00 million. According to the NPV rule, the manager needs to undertake this project. NPV is $70.00 million. According to the NPV rule, the manager should not undertake this project and had better wait for another project with a higher NPV.
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Essentials Of Investments
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
FUNDAMENTALS OF CORPORATE FINANCE
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:
9781260013962
Author:
BREALEY
Publisher:
RENT MCG
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
Foundations Of Finance
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education