Question 7 Part C: Oregon is examining how to allocate funding over the next five years and have arrived at four projects that are in contention. The numerical details are listed below (Oregon uses a MARR of 10% for new projects): Project 105 205 305 405 Initial Cost 2,500,000 2,500,000 3,000,000 2,000,000 Annual Maintenance 250,000 250,000 200,000 300,000 Cost Yearly Benefit 1,000,000 900,000 900,000 1,000,000 Yearly Disbenefit 15,000 10,000 0 100,000 B/C Ratio 1.08 0.98 0.91 1.09 Question 7 Part C: If we assume we have to compute an incremental analysis between Projects 105 and 405, what would the incremental B/C ratio between the two projects be? Enter your answer in the format: 1.23

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question
Question 7 Part C: Oregon is examining how to allocate funding over the next five years and have arrived at four projects that are in contention. The numerical details are listed below
(Oregon uses a MARR of 10% for new projects):
Project
105
205
305
405
Initial Cost
2,500,000 2,500,000 3,000,000 2,000,000
Annual
Maintenance 250,000
250,000 200,000 300,000
Cost
Yearly Benefit
1,000,000
900,000
900,000 1,000,000
Yearly Disbenefit 15,000
10,000
0
100,000
B/C Ratio
1.08
0.98
0.91
1.09
Question 7 Part C: If we assume we have to compute an incremental analysis between Projects 105 and 405, what would the incremental B/C ratio between the two projects be? Enter
your answer in the format: 1.23
Transcribed Image Text:Question 7 Part C: Oregon is examining how to allocate funding over the next five years and have arrived at four projects that are in contention. The numerical details are listed below (Oregon uses a MARR of 10% for new projects): Project 105 205 305 405 Initial Cost 2,500,000 2,500,000 3,000,000 2,000,000 Annual Maintenance 250,000 250,000 200,000 300,000 Cost Yearly Benefit 1,000,000 900,000 900,000 1,000,000 Yearly Disbenefit 15,000 10,000 0 100,000 B/C Ratio 1.08 0.98 0.91 1.09 Question 7 Part C: If we assume we have to compute an incremental analysis between Projects 105 and 405, what would the incremental B/C ratio between the two projects be? Enter your answer in the format: 1.23
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education