Question 3: Calculate the variance for the given data: a) The standard mix to produce one unit of product is as follows: Material A 60 units @ $ 10 per unit Material B 80 units @ $ 15 per unit Material C 100 units @ $ 20 per unit During the month of July, 10 units were actually produced and consumption was as follows: Material A 640 units @ $ 7.50 per unit Material B 950 units @ $ 18.00 per unit Material C 870 units @ $ 22.50 per unit Calculate material variances. b) Standard wage rate is Rs.3 per hour and standard time is 10 hours. But actual wage rate is Rs. 3.5per hour and actual hours used are 12 hours. Calculate Labor cost variance.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Topic Video
Question
Question 3: Calculate the variance for the given data:
a) The standard mix to produce one unit of product is as follows:
Material A 60 units @ $ 10 per unit
Material B 80 units @$ 15 per unit
Material C 100 units @ $ 20 per unit
During the month of July, 10 units were actually produced and consumption was as follows:
Material A 640 units @S 7.50 per unit
Material B 950 units @ $ 18.00 per unit
Material C 870 units @ $ 22.50 per unit
Calculate material variances.
b) Standard wage rate is Rs.3 per hour and standard time is 10 hours. But actual wage rate is Rs. 3.5per hour
and actual hours used are 12 hours. Calculate Labor cost variance.
Transcribed Image Text:Question 3: Calculate the variance for the given data: a) The standard mix to produce one unit of product is as follows: Material A 60 units @ $ 10 per unit Material B 80 units @$ 15 per unit Material C 100 units @ $ 20 per unit During the month of July, 10 units were actually produced and consumption was as follows: Material A 640 units @S 7.50 per unit Material B 950 units @ $ 18.00 per unit Material C 870 units @ $ 22.50 per unit Calculate material variances. b) Standard wage rate is Rs.3 per hour and standard time is 10 hours. But actual wage rate is Rs. 3.5per hour and actual hours used are 12 hours. Calculate Labor cost variance.
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education