Question 3 A producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that the desired cycle time is 12 minutes. Length (minutes) Immediate Tasks predecessor a 3 b 3 a 1 b d. - e 3 d f 2 С, е g f 7 i 4 j 10 i k 7 6. g, k 4 a) Draw the precedence diagram. b) i. Assign tasks to work stations in order of most following tasks. Use greatest positional weight as the tiebreaker. ii. What is the actual cycle time? iii. Determine the % idle time. iv. On a 480 minutes work day, what is the production rate per day? c) Assign tasks to work stations in order of greatest positional weight. Use most i. foliowing tasks as the tiebreaker. ii. What is the actual cycle time? iii. Determine the % idle time. iv On a 480 minutes work day, what is the production rate per day? What is the minimum cycle time that will permit the use of only three workstations? Is this d) cycle time feasible? If you were assigning tasks to workstations in order of most following, and using greatest positional weight as tiebreaker, how would you assign the tasks to workstations?
Question 3 A producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that the desired cycle time is 12 minutes. Length (minutes) Immediate Tasks predecessor a 3 b 3 a 1 b d. - e 3 d f 2 С, е g f 7 i 4 j 10 i k 7 6. g, k 4 a) Draw the precedence diagram. b) i. Assign tasks to work stations in order of most following tasks. Use greatest positional weight as the tiebreaker. ii. What is the actual cycle time? iii. Determine the % idle time. iv. On a 480 minutes work day, what is the production rate per day? c) Assign tasks to work stations in order of greatest positional weight. Use most i. foliowing tasks as the tiebreaker. ii. What is the actual cycle time? iii. Determine the % idle time. iv On a 480 minutes work day, what is the production rate per day? What is the minimum cycle time that will permit the use of only three workstations? Is this d) cycle time feasible? If you were assigning tasks to workstations in order of most following, and using greatest positional weight as tiebreaker, how would you assign the tasks to workstations?
MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
Related questions
Question
![Question 3
A producer of inkjet printers is planning to add a new line of printers, and you have been asked to
balance the process, given the following task times and precedence relationships. Assume that the
desired cycle time is 12 minutes.
Length
(minutes)
Immediate
Tasks
predecessor
a
3
3
a
1
b
d.
e
3
d
f
С, е
g
f
7
i
4
j
10
i
k
7
g, k
a)
Draw the precedence diagram.
b)
i.
Assign tasks to work stations in order of most following tasks. Use greatest
positional weight as the tiebreaker.
ii.
What is the actual cycle time?
iii.
Determine the % idle time.
iv.
On a 480 minutes work day, what is the production rate per day?
с)
i.
foliowing tasks as the tiebreaker.
Assign tasks to work stations in order of greatest positional weight. Use most
ii.
What is the actual cycle time?
iii.
Determine the % idle time.
iv
On a 480 minutes work day, what is the production rate per day?
What is the minimum cycle time that will permit the use of only three workstations? Is this
d)
cycle time feasible? If you were assigning tasks to workstations in order of most following, and using
greatest positional weight as tiebreaker, how would you assign the tasks to workstations?](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F323a54ef-6567-4c9a-a4d1-19f4d0f68684%2Fa69c1146-da31-40ff-aa25-19e2518f7f6a%2Fu6x0jk_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Question 3
A producer of inkjet printers is planning to add a new line of printers, and you have been asked to
balance the process, given the following task times and precedence relationships. Assume that the
desired cycle time is 12 minutes.
Length
(minutes)
Immediate
Tasks
predecessor
a
3
3
a
1
b
d.
e
3
d
f
С, е
g
f
7
i
4
j
10
i
k
7
g, k
a)
Draw the precedence diagram.
b)
i.
Assign tasks to work stations in order of most following tasks. Use greatest
positional weight as the tiebreaker.
ii.
What is the actual cycle time?
iii.
Determine the % idle time.
iv.
On a 480 minutes work day, what is the production rate per day?
с)
i.
foliowing tasks as the tiebreaker.
Assign tasks to work stations in order of greatest positional weight. Use most
ii.
What is the actual cycle time?
iii.
Determine the % idle time.
iv
On a 480 minutes work day, what is the production rate per day?
What is the minimum cycle time that will permit the use of only three workstations? Is this
d)
cycle time feasible? If you were assigning tasks to workstations in order of most following, and using
greatest positional weight as tiebreaker, how would you assign the tasks to workstations?
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 4 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![MATLAB: An Introduction with Applications](https://www.bartleby.com/isbn_cover_images/9781119256830/9781119256830_smallCoverImage.gif)
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
![Probability and Statistics for Engineering and th…](https://www.bartleby.com/isbn_cover_images/9781305251809/9781305251809_smallCoverImage.gif)
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
![Statistics for The Behavioral Sciences (MindTap C…](https://www.bartleby.com/isbn_cover_images/9781305504912/9781305504912_smallCoverImage.gif)
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
![MATLAB: An Introduction with Applications](https://www.bartleby.com/isbn_cover_images/9781119256830/9781119256830_smallCoverImage.gif)
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
![Probability and Statistics for Engineering and th…](https://www.bartleby.com/isbn_cover_images/9781305251809/9781305251809_smallCoverImage.gif)
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
![Statistics for The Behavioral Sciences (MindTap C…](https://www.bartleby.com/isbn_cover_images/9781305504912/9781305504912_smallCoverImage.gif)
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
![Elementary Statistics: Picturing the World (7th E…](https://www.bartleby.com/isbn_cover_images/9780134683416/9780134683416_smallCoverImage.gif)
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
![The Basic Practice of Statistics](https://www.bartleby.com/isbn_cover_images/9781319042578/9781319042578_smallCoverImage.gif)
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
![Introduction to the Practice of Statistics](https://www.bartleby.com/isbn_cover_images/9781319013387/9781319013387_smallCoverImage.gif)
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman