QUESTION [25] Manac Ltd manufactures clothing and uses a standard costing system. The following is the standard variable cost for one of their products: R Material @ R8.00 per kg 20.00 Labour @ 1.5 hrs 22.50 Variable overheads -varying with hours worked: 1.5 hrs @ R6.00 per hour 9.00 -varying with production 7.00 Budgeted sales - 11 700 units Actual results are as follows: Materials purchased 32 000 kg R262 400 Labour (Rate per hour R16.00) R304 000 Variable overheads -varying with hours worked -varying with production Sales R108 300 R 78 000 R624 000 Additional information: The budgeted selling price is R50.00 per unit. 1. 12 000 units were manufactured and sold. 2. There were no completed units, work in progress or material on hand at the beginning or end of the period. 1. Material price variance Required: (5) Calculate and state whether the following variances are favourable / unfavourable: 1. Material quantity variance 2. Labour rate variance 3. Labour efficiency variance 4. Selling price variance (5) (5) (5) (5)
QUESTION [25] Manac Ltd manufactures clothing and uses a standard costing system. The following is the standard variable cost for one of their products: R Material @ R8.00 per kg 20.00 Labour @ 1.5 hrs 22.50 Variable overheads -varying with hours worked: 1.5 hrs @ R6.00 per hour 9.00 -varying with production 7.00 Budgeted sales - 11 700 units Actual results are as follows: Materials purchased 32 000 kg R262 400 Labour (Rate per hour R16.00) R304 000 Variable overheads -varying with hours worked -varying with production Sales R108 300 R 78 000 R624 000 Additional information: The budgeted selling price is R50.00 per unit. 1. 12 000 units were manufactured and sold. 2. There were no completed units, work in progress or material on hand at the beginning or end of the period. 1. Material price variance Required: (5) Calculate and state whether the following variances are favourable / unfavourable: 1. Material quantity variance 2. Labour rate variance 3. Labour efficiency variance 4. Selling price variance (5) (5) (5) (5)
Managerial Accounting: The Cornerstone of Business Decision-Making
7th Edition
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Chapter7: Cost-volume-profit Analysis
Section: Chapter Questions
Problem 46E: Lotts Company produces and sells one product. The selling price is 10, and the unit variable cost is...
Related questions
Question
Answer with explanation this accounting Problem
![QUESTION [25]
Manac Ltd manufactures clothing and uses a standard costing system.
The following is the standard variable cost for one of their products:
R
Material @ R8.00 per kg
20.00
Labour @ 1.5 hrs
22.50
Variable overheads
-varying with hours worked: 1.5 hrs @ R6.00 per hour
9.00
-varying with production
7.00
Budgeted sales - 11 700 units
Actual results are as follows:
Materials purchased 32 000 kg
R262 400
Labour (Rate per hour R16.00)
R304 000
Variable overheads
-varying with hours worked
-varying with production
Sales
R108 300
R 78 000
R624 000
Additional information:
The budgeted selling price is R50.00 per unit.
1. 12 000 units were manufactured and sold.
2. There were no completed units, work in progress or material on hand at the
beginning or end of the period.
1. Material price variance
Required:
(5)
Calculate and state whether the following variances are favourable /
unfavourable:
1. Material quantity variance
2. Labour rate variance
3. Labour efficiency variance
4. Selling price variance
(5)
(5)
(5)
(5)](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F86ab8c7f-244d-4541-bece-4af5893b6d33%2Fce16b607-78c0-4c1f-9b87-611e312f96bc%2F3g1u7ta_processed.jpeg&w=3840&q=75)
Transcribed Image Text:QUESTION [25]
Manac Ltd manufactures clothing and uses a standard costing system.
The following is the standard variable cost for one of their products:
R
Material @ R8.00 per kg
20.00
Labour @ 1.5 hrs
22.50
Variable overheads
-varying with hours worked: 1.5 hrs @ R6.00 per hour
9.00
-varying with production
7.00
Budgeted sales - 11 700 units
Actual results are as follows:
Materials purchased 32 000 kg
R262 400
Labour (Rate per hour R16.00)
R304 000
Variable overheads
-varying with hours worked
-varying with production
Sales
R108 300
R 78 000
R624 000
Additional information:
The budgeted selling price is R50.00 per unit.
1. 12 000 units were manufactured and sold.
2. There were no completed units, work in progress or material on hand at the
beginning or end of the period.
1. Material price variance
Required:
(5)
Calculate and state whether the following variances are favourable /
unfavourable:
1. Material quantity variance
2. Labour rate variance
3. Labour efficiency variance
4. Selling price variance
(5)
(5)
(5)
(5)
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you

Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning

Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College

Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning

Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College

Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning