question 2 [20 Marks] Assume that operations on a work package were expected to cost £2,500. After 4 weeks they were scheduled to have cost £1,900 but instead have cost £1,500 and it is estimated that 50% of the work package has been completed. a) b) c) Assume that the project costs are evenly spread throughout the duration of the work package, make a rough sketch of typical cost versus time curves for the Planned Value (PV), Actual Cost (AC) and Earned Value (EV). [3 marks] 018-19 Explain why Earned Value improves the projected outcome analysis of a project, and how this might determine the cancellation of a programme of work. [3 Marks] Calculate the: i. ii. iii. iv. V. vi. VII. Cost Variance Schedule Variance Cost Performance Index Schedule Performance Index Cost-Schedule Index Estimated cost to complete (ETC) Estimated cost at completion (EAC) [2 marks] [2 marks] [2 Marks] Question 3 [10 Marks] Portsmouth city council wants the municipal engineer to evaluate three alternatives for supplementing the city water supply. The first alternative is to continue deep well pumping at an annual cost of $10,500. The second alternative is to install an 18" pipeline from a surface reservoir. First cost is $25,000 and annual pumping cost is $7000. The third alternative is to install a 24" pipeline from the reservoir at a first cost of $34,000 and annual pumping cost of $5000. Life of all alternatives is 20 years. For the second and third alternatives, salvage value is 10% of first cost. With interest at 8%, which alternative should the engineer recommend? Use present worth analysis. realme Shot on realme 9i [2 Marks] [2 marks] [2 marks] [2 marks] Page 2 of 5 2024 01 13 15:46
question 2 [20 Marks] Assume that operations on a work package were expected to cost £2,500. After 4 weeks they were scheduled to have cost £1,900 but instead have cost £1,500 and it is estimated that 50% of the work package has been completed. a) b) c) Assume that the project costs are evenly spread throughout the duration of the work package, make a rough sketch of typical cost versus time curves for the Planned Value (PV), Actual Cost (AC) and Earned Value (EV). [3 marks] 018-19 Explain why Earned Value improves the projected outcome analysis of a project, and how this might determine the cancellation of a programme of work. [3 Marks] Calculate the: i. ii. iii. iv. V. vi. VII. Cost Variance Schedule Variance Cost Performance Index Schedule Performance Index Cost-Schedule Index Estimated cost to complete (ETC) Estimated cost at completion (EAC) [2 marks] [2 marks] [2 Marks] Question 3 [10 Marks] Portsmouth city council wants the municipal engineer to evaluate three alternatives for supplementing the city water supply. The first alternative is to continue deep well pumping at an annual cost of $10,500. The second alternative is to install an 18" pipeline from a surface reservoir. First cost is $25,000 and annual pumping cost is $7000. The third alternative is to install a 24" pipeline from the reservoir at a first cost of $34,000 and annual pumping cost of $5000. Life of all alternatives is 20 years. For the second and third alternatives, salvage value is 10% of first cost. With interest at 8%, which alternative should the engineer recommend? Use present worth analysis. realme Shot on realme 9i [2 Marks] [2 marks] [2 marks] [2 marks] Page 2 of 5 2024 01 13 15:46
Introductory Circuit Analysis (13th Edition)
13th Edition
ISBN:9780133923605
Author:Robert L. Boylestad
Publisher:Robert L. Boylestad
Chapter1: Introduction
Section: Chapter Questions
Problem 1P: Visit your local library (at school or home) and describe the extent to which it provides literature...
Related questions
Question
its previous question
![question 2 [20 Marks]
Assume that operations on a work package were expected to cost £2,500. After 4 weeks they were
scheduled to have cost £1,900 but instead have cost £1,500 and it is estimated that 50% of the work package
has been completed.
a)
b)
c)
Assume that the project costs are evenly spread throughout the duration of the work package,
make a rough sketch of typical cost versus time curves for the Planned Value (PV), Actual Cost
(AC) and Earned Value (EV).
[3 marks]
018-19
Explain why Earned Value improves the projected outcome analysis of a project, and how this
might determine the cancellation of a programme of work.
[3 Marks]
Calculate the:
i.
ii.
iii.
iv.
V.
vi.
VII.
Cost Variance
Schedule Variance
Cost Performance Index
Schedule Performance Index
Cost-Schedule Index
Estimated cost to complete (ETC)
Estimated cost at completion (EAC)
[2 marks]
[2 marks]
[2 Marks]
Question 3 [10 Marks]
Portsmouth city council wants the municipal engineer to evaluate three alternatives for supplementing the
city water supply. The first alternative is to continue deep well pumping at an annual cost of $10,500. The
second alternative is to install an 18" pipeline from a surface reservoir. First cost is $25,000 and annual
pumping cost is $7000. The third alternative is to install a 24" pipeline from the reservoir at a first cost of
$34,000 and annual pumping cost of $5000. Life of all alternatives is 20 years. For the second and third
alternatives, salvage value is 10% of first cost. With interest at 8%, which alternative should the engineer
recommend? Use present worth analysis.
realme Shot on realme 9i
[2 Marks]
[2 marks]
[2 marks]
[2 marks]
Page 2 of 5
2024 01 13 15:46](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F5078b36b-0919-4e29-b4ac-2f7061cde72a%2F7fdd3f57-1720-4ed4-9af6-7ee19f7a2496%2Fsgooljo_processed.jpeg&w=3840&q=75)
Transcribed Image Text:question 2 [20 Marks]
Assume that operations on a work package were expected to cost £2,500. After 4 weeks they were
scheduled to have cost £1,900 but instead have cost £1,500 and it is estimated that 50% of the work package
has been completed.
a)
b)
c)
Assume that the project costs are evenly spread throughout the duration of the work package,
make a rough sketch of typical cost versus time curves for the Planned Value (PV), Actual Cost
(AC) and Earned Value (EV).
[3 marks]
018-19
Explain why Earned Value improves the projected outcome analysis of a project, and how this
might determine the cancellation of a programme of work.
[3 Marks]
Calculate the:
i.
ii.
iii.
iv.
V.
vi.
VII.
Cost Variance
Schedule Variance
Cost Performance Index
Schedule Performance Index
Cost-Schedule Index
Estimated cost to complete (ETC)
Estimated cost at completion (EAC)
[2 marks]
[2 marks]
[2 Marks]
Question 3 [10 Marks]
Portsmouth city council wants the municipal engineer to evaluate three alternatives for supplementing the
city water supply. The first alternative is to continue deep well pumping at an annual cost of $10,500. The
second alternative is to install an 18" pipeline from a surface reservoir. First cost is $25,000 and annual
pumping cost is $7000. The third alternative is to install a 24" pipeline from the reservoir at a first cost of
$34,000 and annual pumping cost of $5000. Life of all alternatives is 20 years. For the second and third
alternatives, salvage value is 10% of first cost. With interest at 8%, which alternative should the engineer
recommend? Use present worth analysis.
realme Shot on realme 9i
[2 Marks]
[2 marks]
[2 marks]
[2 marks]
Page 2 of 5
2024 01 13 15:46
AI-Generated Solution
Unlock instant AI solutions
Tap the button
to generate a solution
Recommended textbooks for you

Introductory Circuit Analysis (13th Edition)
Electrical Engineering
ISBN:
9780133923605
Author:
Robert L. Boylestad
Publisher:
PEARSON

Delmar's Standard Textbook Of Electricity
Electrical Engineering
ISBN:
9781337900348
Author:
Stephen L. Herman
Publisher:
Cengage Learning

Programmable Logic Controllers
Electrical Engineering
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education

Introductory Circuit Analysis (13th Edition)
Electrical Engineering
ISBN:
9780133923605
Author:
Robert L. Boylestad
Publisher:
PEARSON

Delmar's Standard Textbook Of Electricity
Electrical Engineering
ISBN:
9781337900348
Author:
Stephen L. Herman
Publisher:
Cengage Learning

Programmable Logic Controllers
Electrical Engineering
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education

Fundamentals of Electric Circuits
Electrical Engineering
ISBN:
9780078028229
Author:
Charles K Alexander, Matthew Sadiku
Publisher:
McGraw-Hill Education

Electric Circuits. (11th Edition)
Electrical Engineering
ISBN:
9780134746968
Author:
James W. Nilsson, Susan Riedel
Publisher:
PEARSON

Engineering Electromagnetics
Electrical Engineering
ISBN:
9780078028151
Author:
Hayt, William H. (william Hart), Jr, BUCK, John A.
Publisher:
Mcgraw-hill Education,