Question 1 A. On a project, the contractor failed to complete the project on time and the project was terminated. Because of the urgency involved to complete the project, another Contractor 'B' was asked to immediately takeover and proceed with the works without going for a tender or entering into a written contract. Assuming you are the contract manager for the Contractor 'B’, what advice would you give to your company on the following: Offer, Acceptance, Consideration, Mutuality of obligations, Competency and capacity before proceeding to start working?
Question 1 A. On a project, the contractor failed to complete the project on time and the project was terminated. Because of the urgency involved to complete the project, another Contractor 'B' was asked to immediately takeover and proceed with the works without going for a tender or entering into a written contract. Assuming you are the contract manager for the Contractor 'B’, what advice would you give to your company on the following: Offer, Acceptance, Consideration, Mutuality of obligations, Competency and capacity before proceeding to start working?
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter13: Pricing Subcontractors' Work
Section: Chapter Questions
Problem 2RQ
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,