Q4: A road is to be redesigned using a parabolic vertical curve to provide clearance beneath a bridge (see Figure below). The (PC OR PVC) has chainage 1140.00m, with an RL of 125.536m. A bridge at chainage 1300.00 has an RL = 128.5m at its lowest point. You must provide 4.5m clearance from the underside of the bridge, and the parabola will finish with a succeeding gradient, G 2 = +3.6%. G1= ? 1. What is the length of the curve? 2. What is the initial gradient G1?( PC Ch 1140 RL 125.536 G1 = ? J 11 Point PVC PVT Easting (m) 122.8 326.1 Here Ah = 4.5 P Northing (m) 40.2 76.3 Ch 1300 RL 128.5 G2 = +3.6% PT RL=124.00 Elevation (m) 125.536 ?

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Q4: A road is to be redesigned using a parabolic vertical curve to provide clearance beneath a bridge
(see Figure below). The (PC OR PVC) has chainage 1140.00m, with an RL of 125.536m. A bridge at
chainage 1300.00 has an RL = 128.5m at its lowest point. You must provide 4.5m clearance from the
underside of the bridge, and the parabola will finish with a succeeding gradient, G 2=+3.6 %. G1= ?
1. What is the length of the curve?
2. What is the initial gradient G1?
PC
Ch 1140
RL 125.536
G1= ?
L =?
Point
PVC
PVT
Easting
(m)
122.8
326.1
Here De
bridkje
Ah = 4.5
Northing
(m)
Ch 1300
RL 128.5
40.2
76.3
G2 = +3.6%
RL = 124.00
PT
Elevation
125.536
?
Transcribed Image Text:Q4: A road is to be redesigned using a parabolic vertical curve to provide clearance beneath a bridge (see Figure below). The (PC OR PVC) has chainage 1140.00m, with an RL of 125.536m. A bridge at chainage 1300.00 has an RL = 128.5m at its lowest point. You must provide 4.5m clearance from the underside of the bridge, and the parabola will finish with a succeeding gradient, G 2=+3.6 %. G1= ? 1. What is the length of the curve? 2. What is the initial gradient G1? PC Ch 1140 RL 125.536 G1= ? L =? Point PVC PVT Easting (m) 122.8 326.1 Here De bridkje Ah = 4.5 Northing (m) Ch 1300 RL 128.5 40.2 76.3 G2 = +3.6% RL = 124.00 PT Elevation 125.536 ?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Intersection design
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning