Question
Q4) A project consists of (6) activities and completion time are given below
i) Draw the project Network.
ii) Find the critical path analysis.
activity
Immediate
Completion
predecessor
time
A
3
A
8
7
12
B,D
10
F
C,E
20
Transcribed Image Text:Q4) A project consists of (6) activities and completion time are given below i) Draw the project Network. ii) Find the critical path analysis. activity Immediate Completion predecessor time A 3 A 8 7 12 B,D 10 F C,E 20
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Algebra & Trigonometry with Analytic Geometry
Algebra & Trigonometry with Analytic Geometry
Algebra
ISBN:
9781133382119
Author:
Swokowski
Publisher:
Cengage