Q4) A project consists of (6) activities and completion time are given below i) Draw the project Network. ii) Find the critical path analysis. activity Immediate Completion predecessor time A A C 7 12 E B,D 10 F C,E 20 3.

Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question
Q4) A project consists of (6) activities and completion time are given below
i) Draw the project Network.
ii) Find the critical path analysis.
activity
Immediate
Completion
predecessor
time
A
3
A
8
7
12
B,D
10
F
C,E
20
Transcribed Image Text:Q4) A project consists of (6) activities and completion time are given below i) Draw the project Network. ii) Find the critical path analysis. activity Immediate Completion predecessor time A 3 A 8 7 12 B,D 10 F C,E 20
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Basic Technical Mathematics
Basic Technical Mathematics
Advanced Math
ISBN:
9780134437705
Author:
Washington
Publisher:
PEARSON
Topology
Topology
Advanced Math
ISBN:
9780134689517
Author:
Munkres, James R.
Publisher:
Pearson,