Problem 4 On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is recognizes Data on this project for 2022-2024 follow: estimated to cost P31,200,000. The company construction revenue over time. Contract Costs Est'd Costs incurred Billings 10,500,000 12,500,000 14,440,000 to Complete 20,540,000 13,156,000 2022 5,460,000 9,984,000 15,756,000 2023 2024 The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. contract was delayed for 8 weeks In 2024, the What is the gross profit for 2024? 1,164,000 1,466,400 1,724,000 1,824,000 А. C. в. D.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Please present solution in an excel accompanied with explanations. Thank you so much!

PROBLEM:

Problem 4
On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which
is
estimated
recognizes
Data on this project for 2022-2024 follow:
to
Cost
P31,200,000.
The
company
construction
revenue over time.
Contract
Costs
Est'd Costs
incurred
Billings
10,500,000
12,500,000
14,440,000
5,460,000
9,984,000
15,756,000
to Complete
20,540,000
13,156,000
2022
2023
2024
The contract contains a penalty clause that penalizes the company a reduction
of P70,000 from the contract price for every week of delay.
contract was delayed for 8 weeks
In 2024,
the
What is the gross profit for 2024?
1,164,000
1,466,400
1,724,000
1,824,000
A.
С.
В.
D.
Transcribed Image Text:Problem 4 On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated recognizes Data on this project for 2022-2024 follow: to Cost P31,200,000. The company construction revenue over time. Contract Costs Est'd Costs incurred Billings 10,500,000 12,500,000 14,440,000 5,460,000 9,984,000 15,756,000 to Complete 20,540,000 13,156,000 2022 2023 2024 The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. contract was delayed for 8 weeks In 2024, the What is the gross profit for 2024? 1,164,000 1,466,400 1,724,000 1,824,000 A. С. В. D.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 7 steps with 5 images

Blurred answer
Knowledge Booster
Personal Financial Statements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education