Problem 11: Materials, Labor and Factory Overhead Variances Julie Corporation uses a standard cost system and has the following standard variable costs.
Problem 11: Materials, Labor and Factory Overhead Variances Julie Corporation uses a standard cost system and has the following standard variable costs.
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
100%
Compute for Requirements #7,8,9
![Froblem 11: Materials, Labor and Factory Overhead Variances
Julie Corporation uses a standard cost system and has the following standard
variable costs.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fd236e8c2-85a0-4752-b899-588581758f1b%2F94b7f7c1-1363-49dd-940e-82b0abe9c067%2Faw3vo6p_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Froblem 11: Materials, Labor and Factory Overhead Variances
Julie Corporation uses a standard cost system and has the following standard
variable costs.
![Standard Price or Rate
P6.00 per meter
Direct Materials
Direct Labor
Variable Factory Overhead
P3.00 per direct labor hour
Factory overhead is applied to production based on direct labor hours. During
the month of February, 5,000 units were produced and sold to custorners. The
following are the selected production data for the month:
Materials
Direct
Labor
P52,500
Variable
used
P84,000
P75,000
P6,000 U
FOH
P21,000
P18,000
Standard Cost allowed
Actual cost incurred
Materials Quantity variance
Actual direct labor hours
Standard FOH rate per direct labor hour
Standard Price per meter
7,500 hours
P3.00/hr.
P6.00 /m.
The difference between the standard and actual cost per unit produced is PO.15
favorable.
Required: Compute the following:
1. The standard cost per unit of product.
2. The actual cost per unit of product.
3. Standard Quantity per unit.
4. Material Price variance.
5. Standard direct labor rate per hour.
6. Labor Rate variance.
7. Labor Efficiency variance
8. Variable Factory overhead spending variance.
9. Variable Factory overhead efficiency variance.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fd236e8c2-85a0-4752-b899-588581758f1b%2F94b7f7c1-1363-49dd-940e-82b0abe9c067%2Flgj3kke_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Standard Price or Rate
P6.00 per meter
Direct Materials
Direct Labor
Variable Factory Overhead
P3.00 per direct labor hour
Factory overhead is applied to production based on direct labor hours. During
the month of February, 5,000 units were produced and sold to custorners. The
following are the selected production data for the month:
Materials
Direct
Labor
P52,500
Variable
used
P84,000
P75,000
P6,000 U
FOH
P21,000
P18,000
Standard Cost allowed
Actual cost incurred
Materials Quantity variance
Actual direct labor hours
Standard FOH rate per direct labor hour
Standard Price per meter
7,500 hours
P3.00/hr.
P6.00 /m.
The difference between the standard and actual cost per unit produced is PO.15
favorable.
Required: Compute the following:
1. The standard cost per unit of product.
2. The actual cost per unit of product.
3. Standard Quantity per unit.
4. Material Price variance.
5. Standard direct labor rate per hour.
6. Labor Rate variance.
7. Labor Efficiency variance
8. Variable Factory overhead spending variance.
9. Variable Factory overhead efficiency variance.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 4 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education