Please do not give solution in image formate thanku Ann Chovies, owner of the Perfect Pasta Pizza Parlor, uses 40 pounds of pepperoni each day in preparing pizzas. There are 300 working days in a year. Order costs for pepperoni are $10.00 per order, and carrying costs are $6 per pound per year. Lead time for each order is 5 days, and the pepperoni itself costs $5.00 per pound. If she were to order 80 pounds of pepperoni at a time, what would be the average inventory level? Round your answers to zero decimal digits. 35 pounds 60 pounds None of the other choices are correct 40 pounds 25 pounds 2) If she were to order 80 pounds of pepperoni at a time, what would be the length of an order cycle? Round your answers to zero decimal digits. None of the other choices are correct 2 days 4 days 3 days 0.4 days
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Please do not give solution in image formate thanku
Ann Chovies, owner of the Perfect Pasta Pizza Parlor, uses 40 pounds of pepperoni each day in preparing pizzas. There are 300 working days in a year. Order costs for pepperoni are $10.00 per order, and carrying costs are $6 per pound per year. Lead time for each order is 5 days, and the pepperoni itself costs $5.00 per pound.
- If she were to order 80 pounds of pepperoni at a time, what would be the average inventory level? Round your answers to zero decimal digits.
35 pounds
60 pounds
None of the other choices are correct
40 pounds
25 pounds
2) If she were to order 80 pounds of pepperoni at a time, what would be the length of an order cycle? Round your answers to zero decimal digits.
None of the other choices are correct
2 days
4 days
3 days
0.4 days
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 5 images