Plan production for a four-month period: February through May.  For February and March, you should produce to exact demand forecast.  For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May.  However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders occur.  There are 100 workers on January 31.  You are given the following demand forecast: February, 90,000; March 65,000; April 110,000; May, 55,000.  Productivity is four units per worker hour, eight hours per day, 20 days per month.  Assume zero inventory on February 1.  Costs are hiring, $50 per new worker; layoff, $70 per worker laid off; inventory holding, $10 per unit-month; straight-time labor, $10 per hour; overtime, $15 per hour; backorder, $20 per unit a. Find the total cost of this plan?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Plan production for a four-month period: February through May.  For February and March, you should produce to exact demand forecast.  For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May.  However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders occur.  There are 100 workers on January 31.  You are given the following demand forecast: February, 90,000; March 65,000; April 110,000; May, 55,000.  Productivity is four units per worker hour, eight hours per day, 20 days per month.  Assume zero inventory on February 1.  Costs are hiring, $50 per new worker; layoff, $70 per worker laid off; inventory holding, $10 per unit-month; straight-time labor, $10 per hour; overtime, $15 per hour; backorder, $20 per unit

a. Find the total cost of this plan?

 

**Relevant Information:**

- Backorder cost per unit: $20.00
- Holding cost per unit: $10.00
- Number of workers at the end: 100
- Hiring cost per worker: $50.00
- Layoff cost per worker: $70.00
- Production time (hours) per unit: 0.25
- Straight time labor cost per hour: $10.00
- Overtime labor cost per hour: $15.00
- Working time (hours/day): 8.00
- Work days per month: 20.00
- Beginning inventory: 0

**Aggregate Production Planning Requirements:**

| Time Period       | February | March | April | May |
|--------------------|----------|-------|-------|-----|
| Forecast              |              |           |         |         |
| **Beginning Inventory** |              |           |         |         |
| Production Required (Forecast - Beginning inventory) |              |           |         |         |
| Production hours required (# units × Production Time per unit) |              |           |         |         |
| **Regular workforce** |              |           |         |         |
| Regular production (Production hrs available/Labor hrs required per unit) |              |           |         |         |
| Overtime hours |              |           |         |         |
| **Overtime production** |              |           |         |         |
| Total production (Production hours required/Production time per unit) |              |           |         |         |
| Ending Inventory (Beginning inventory + Actual production - Demand forecast) |              |           |         |         |
| Ending backorders |              |           |         |         |
| Workers hired |              |           |         |         |
| Workers laid off |              |           |         |         |
| Straight Time (Production hrs available × Straight time labor cost) |              |           |         |         |
| **Overtime:** |              |           |         |         |
| Inventory cost |              |           |         |         |
| Backorder cost |              |           |         |         |
| Hiring cost |              |           |         |         |
| Layoff cost |              |           |         |         |
| **Total costs** |              |           |         |         |
| **Total Cost** |              |           |         |         |

This table provides a framework for planning and calculating various
Transcribed Image Text:**Relevant Information:** - Backorder cost per unit: $20.00 - Holding cost per unit: $10.00 - Number of workers at the end: 100 - Hiring cost per worker: $50.00 - Layoff cost per worker: $70.00 - Production time (hours) per unit: 0.25 - Straight time labor cost per hour: $10.00 - Overtime labor cost per hour: $15.00 - Working time (hours/day): 8.00 - Work days per month: 20.00 - Beginning inventory: 0 **Aggregate Production Planning Requirements:** | Time Period | February | March | April | May | |--------------------|----------|-------|-------|-----| | Forecast | | | | | | **Beginning Inventory** | | | | | | Production Required (Forecast - Beginning inventory) | | | | | | Production hours required (# units × Production Time per unit) | | | | | | **Regular workforce** | | | | | | Regular production (Production hrs available/Labor hrs required per unit) | | | | | | Overtime hours | | | | | | **Overtime production** | | | | | | Total production (Production hours required/Production time per unit) | | | | | | Ending Inventory (Beginning inventory + Actual production - Demand forecast) | | | | | | Ending backorders | | | | | | Workers hired | | | | | | Workers laid off | | | | | | Straight Time (Production hrs available × Straight time labor cost) | | | | | | **Overtime:** | | | | | | Inventory cost | | | | | | Backorder cost | | | | | | Hiring cost | | | | | | Layoff cost | | | | | | **Total costs** | | | | | | **Total Cost** | | | | | This table provides a framework for planning and calculating various
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.