Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to five separate activity pools. The budgeted activity cost and activity base data by product are as follows: Procurement Scheduling Materials handling Product development Production Activity Base $370,000 Number of purchase orders 250,000 Number of production orders 500,000 Number of moves 730,000 Number of engineering changes 1,500,000 Machine hours Activity Cost Number of Purchase Orders Number of Number Number of Production Engineering Orders Changes 300 Moves 1,400 150 10 Disk drives 4,000 2,000 Tape drives 4,000 8,000 Wire drives 12,000 800 4,000 10,000 The activity rate (rounded to the nearest cent) for the procurement activity cost pool is O a. $18.50 per purchase order O b. $37 per purchase order O c. $43.53 per purchase order O d. $15.42 per purchase order 800 10 Machine Hours 25 Number of Units 2,000 4,000 2,500
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to five separate activity pools. The budgeted activity cost and activity base data by product are as follows: Procurement Scheduling Materials handling Product development Production Activity Base $370,000 Number of purchase orders 250,000 Number of production orders 500,000 Number of moves 730,000 Number of engineering changes 1,500,000 Machine hours Activity Cost Number of Purchase Orders Number of Number Number of Production Engineering Orders Changes 300 Moves 1,400 150 10 Disk drives 4,000 2,000 Tape drives 4,000 8,000 Wire drives 12,000 800 4,000 10,000 The activity rate (rounded to the nearest cent) for the procurement activity cost pool is O a. $18.50 per purchase order O b. $37 per purchase order O c. $43.53 per purchase order O d. $15.42 per purchase order 800 10 Machine Hours 25 Number of Units 2,000 4,000 2,500
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
Please do not give solution in image format thanku
![Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The
indirect labor can be traced to five separate activity pools. The budgeted activity cost and activity base data by product are as follows:
Procurement
Scheduling
Materials handling
Product development
Production
Disk drives
Tape drives
Wire drives
Activity Base
$370,000 Number of purchase orders
250,000
Number of production orders
500,000
Number of moves
730,000
Number of engineering changes
1,500,000
Machine hours
Activity Cost
Number of
Purchase
Orders
Number of Number Number of
Production
of
Orders
Moves
c. $43.53 per purchase order
O d. $15.42 per purchase order
300
150
1,400
800
Engineering
Changes
4,000
2,000
4,000
8,000
12,000
4,000
10,000
The activity rate (rounded to the nearest cent) for the procurement activity cost pool is
O a. $18.50 per purchase order
O b. $37 per purchase order
800
10
10
Machine
Hours
25
Number
of
Units
2,000
4,000
2,500
( Previous
Next](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fd11c14b0-a36a-4ae1-afa6-69bf92ce8853%2Fe75ac294-1a54-46cd-a223-80c7f15f70da%2F3e9i7luh_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The
indirect labor can be traced to five separate activity pools. The budgeted activity cost and activity base data by product are as follows:
Procurement
Scheduling
Materials handling
Product development
Production
Disk drives
Tape drives
Wire drives
Activity Base
$370,000 Number of purchase orders
250,000
Number of production orders
500,000
Number of moves
730,000
Number of engineering changes
1,500,000
Machine hours
Activity Cost
Number of
Purchase
Orders
Number of Number Number of
Production
of
Orders
Moves
c. $43.53 per purchase order
O d. $15.42 per purchase order
300
150
1,400
800
Engineering
Changes
4,000
2,000
4,000
8,000
12,000
4,000
10,000
The activity rate (rounded to the nearest cent) for the procurement activity cost pool is
O a. $18.50 per purchase order
O b. $37 per purchase order
800
10
10
Machine
Hours
25
Number
of
Units
2,000
4,000
2,500
( Previous
Next
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education