For the project consisting of activities shown in the
table, the time of the completion of the project is
IHGFED CBA A Active
E,G D B,A B,A CA
-
--
5 3 7 26 4 5 3 day
O
O
O
4
12 يوم
16 يوم
14 يوم
Transcribed Image Text:For the project consisting of activities shown in the table, the time of the completion of the project is IHGFED CBA A Active E,G D B,A B,A CA - -- 5 3 7 26 4 5 3 day O O O 4 12 يوم 16 يوم 14 يوم
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College