ASSIGNMENT PROBLEM Assignment problems are LPP problems where a project/work is assigned to a specific machine or to an individual. It is an one-to one pairing. www Mr. Pat, the manager of MTVM Machine Shop plans to assign his four projects to the following contractors, TV Engineering, JPAT Enterprise, HP Construction and VH Materials Engineering. Construct a problem and solve. Objective is minimizing the cost of the project. Note: The labelling of the table should be like this. PROJECT1 P2 P3 P4 TV ENGINEERING 290 360 295 330 JPAT Enterprise 195 240 285 305 HP Construction 260 215 300 335 VH Materials Eng'g 200 255 285 320
ASSIGNMENT PROBLEM Assignment problems are LPP problems where a project/work is assigned to a specific machine or to an individual. It is an one-to one pairing. www Mr. Pat, the manager of MTVM Machine Shop plans to assign his four projects to the following contractors, TV Engineering, JPAT Enterprise, HP Construction and VH Materials Engineering. Construct a problem and solve. Objective is minimizing the cost of the project. Note: The labelling of the table should be like this. PROJECT1 P2 P3 P4 TV ENGINEERING 290 360 295 330 JPAT Enterprise 195 240 285 305 HP Construction 260 215 300 335 VH Materials Eng'g 200 255 285 320
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter6: Optimization Models With Integer Variables
Section: Chapter Questions
Problem 100P
Related questions
Question
Assignment problems are LPP problems where a project/work is assigned to a specific machine or to an individual. It is a one-to-one pairing.
Mr. Pat, the manager of MTVM Machine Shop plans to assign his four projects to the following contractors, TV Engineering, JPAT Enterprise, HP Construction and VH Materials Engineering. Construct a problem and solve the Objective is minimizing the cost of the project.
Note: The labelling of the table should be like this.

Transcribed Image Text:ASSIGNMENT PROBLEM
Assignment problems are LPP problems where a project/work is assigned to a
specific machine or to an individual. It is an one-to one pairing.
www
Mr. Pat, the manager of MTVM Machine Shop plans to assign his four projects to
the following contractors, TV Engineering, JPAT Enterprise, HP Construction and VH
Materials Engineering. Construct a problem and solve. Objective is minimizing the
cost of the project.
Note: The labelling of the table should be like this.
PROJECT1
P2
P3
P4
TV ENGINEERING
290
360
295
330
JPAT Enterprise
195
240
285
305
HP Construction
260
215
300
335
VH Materials Eng'g
200
255
285
320
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 4 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,