on the land and built a new factory. Equipment was also acquired for Miller Corp. acquired a tract of land, demolished the unusable building the factory. The following inflows and outflows occurred: While searching for a suitable block of land, Miller Corp. placed an option to buy with three real estate agentS at a cost of P1,000 each. One of these blocks of land was later acquired. Payment of option fees Receipt of loan from bank Payment to settlement agent for title search, stamp duties and settlement fees P 3,000 4,000,000 100,000 Payment for property taxes in arrears on building and land 50,000 1,000,000 120,000 55,000 230,000 120,000 34,000 2,400,000 Payment for land Payment for demolition of current building on land Proceeds from sale of material from old building Payment to architect Payment to council for approval of building construction Payment for safety fence around construction site Payment to construction contractor for factory building Payment for external driveways, parking bays and safety lighting Payment for safety inspection on building Payment for equipment Payment of freight and insurance costs on delivery of equipment Payment of installation costs on equipment Payment for safety equipment surrounding equipment Payment for removal of safety fence Payment for new fence surrounding the factory Payment for advertisements about the forthcoming factory and its benefits to the local community Payment for opening ceremony 540,000 30,000 640,000 56,000 120,000 110,000 20,000 80,000 5,000 60,000 Required: cost of land, land improvements, building and Compute the equipment.
on the land and built a new factory. Equipment was also acquired for Miller Corp. acquired a tract of land, demolished the unusable building the factory. The following inflows and outflows occurred: While searching for a suitable block of land, Miller Corp. placed an option to buy with three real estate agentS at a cost of P1,000 each. One of these blocks of land was later acquired. Payment of option fees Receipt of loan from bank Payment to settlement agent for title search, stamp duties and settlement fees P 3,000 4,000,000 100,000 Payment for property taxes in arrears on building and land 50,000 1,000,000 120,000 55,000 230,000 120,000 34,000 2,400,000 Payment for land Payment for demolition of current building on land Proceeds from sale of material from old building Payment to architect Payment to council for approval of building construction Payment for safety fence around construction site Payment to construction contractor for factory building Payment for external driveways, parking bays and safety lighting Payment for safety inspection on building Payment for equipment Payment of freight and insurance costs on delivery of equipment Payment of installation costs on equipment Payment for safety equipment surrounding equipment Payment for removal of safety fence Payment for new fence surrounding the factory Payment for advertisements about the forthcoming factory and its benefits to the local community Payment for opening ceremony 540,000 30,000 640,000 56,000 120,000 110,000 20,000 80,000 5,000 60,000 Required: cost of land, land improvements, building and Compute the equipment.
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
Required:
- Compute the cost of land, land improvements, building, and equipment.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education