On January 1, 2022, Charis Company adopted a plan anuary 1, 2026 at an estimated cost of P20,000,000 eginning December 31, 2022 that will earn interes
Q: Indiana Company began a construction project in 2024 with a contract price of $165 million to be…
A: Contract accounting might be characterized as "the efficient account of the work done under each…
Q: How much gross profit should be reported for 2021?
A: Percentage-of-Completion Method-: The Percentage of Completion Method comes under the revenue…
Q: U.S. Metallurgical Inc. reported the following balances in its financial statements and disclosure…
A: Note: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question…
Q: U.S. Metallurgical Incorporated reported the following balances in its financial statements and…
A: "Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: ary 1, 2024 1, 2024 30, 2024 ber 1, 2024 ary 31, 2025 30, 2025 st 31, 2025 $ 1,500,000 1,200,000…
A: Interest capitalized is based on Weighted Average Accumulated Expenditures and capitalization rate…
Q: On January 1, 2023, Falcon Construction Ltd. starts a construction project for $4,500,000. Relevant…
A: Percentage of completion Method In long-term contracts, businesses can recognize revenue on a…
Q: In 2024, Cupid Construction Company (CCC) began work on a two-year fixed price contract project. CCC…
A: The objective of the question is to calculate the estimated remaining construction costs on the…
Q: On January 1, 2024, the Mason Manufacturing Company began construction of a building to be used as…
A: Borrowing costs are the cost that is incurred with respect to the borrowing of funds i.e, interest…
Q: Required: 1. What is the pension expense at the end of 2021? 2. What is the projected benefit…
A: “Hey, since there are multiple requirements posted, we will answer first three requirements. If you…
Q: On January 2, 2020, Brook Company acquired machinery by Issuing a 5%, $350,000 note due in 5 years…
A: Current portion of liability means the obligation that an entity would settle within a year and…
Q: Martinez Furniture started construction of a combination office and warehouse building for its own…
A: Long term debt is that kind of debt which is presented differently from short term debt and also…
Q: 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara…
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: To calculate the amount of revenue and gross profit (loss) to be recognized in each of the three…
Q: ZEN Ltd signs a contract on 30 June 2019, agreeing to build a bridge for XYN at a contract price of…
A: Cost(an input measure) method:- In this approach, the percentage of completion is based on the costs…
Q: 4SMC entered into a long-term construction contract for 3 years. Contract price agreed was…
A: When the outcome of a construction contract can be estimated reliably, contract revenue and contract…
Q: n 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: The question is based on the concept of Financial Accounting. Construction contracts are the…
Q: Build a Bridge Inc. prepares its financial statements in accordance with IFRS. The company started…
A: The percentage of completion approach is used to recognise income and expenses related to long-term…
Q: The Leto Construction Company began work on a $12.000 contract on 1/1/20. Planned completion was in…
A: Construction in progress is equal to the contract value multiplied by the percentage of completion.…
Q: On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate. The building…
A: Weighted average rate of debt = Total Interest Amount / Total Borrowings Amount
Q: a) Using percentage-of-completion method, prepare schedules to compute the profit and loss to be…
A: The amount earned from the business operation is known as operating income, but when the expenses to…
Step by step
Solved in 2 steps with 1 images
- In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year 2024 $ 2,523,000 6,177,000 2,070,000 2025 $ 3,177,000 1,800,000 3,630,000 2026 $ 1,980,000 0 Cash collections during the year 1,835,000 3,400,000 4,300,000 4,765,000 Westgate recognizes revenue over time according to percentage of completion. Problem 6-10 (Algo) Part 5 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign. Costs incurred during the year Estimated costs to complete as of year-end 2024 $…Beck Construction Company began work on a new building project on January 1, 2023. The project is to be completed by December 31, 2025, for a fixed price of $159 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years 2023 2024 2025 Actual costs incurred in each year $ 43 million $ 71 million $ 48 million Years 2023 2024 2025 Required: What amount of gross profit (or loss) would Beck record on this project in each year, assuming that Beck recognizes revenue for this project upon completion of the project? Note: Enter "None" if there is no requirement of recognizing profit or loss. Loss amounts should be indicated with a minus sign. Enter your answers in millions (i.e., 10,000,000 should be entered as 10). Gross Profit (or Loss) recognized Gross profit Gross profit Gross profit Estimated remaining costs to complete t project (measured at December 31 of each year) $ 86 million. $ 71…In 2021, the Kokosing Construction Company of Columbus, Ohio entered into a contract to construct a road for Franklin County for $20,000,000. The road was completed in 2023. Information pertaining to the contract is provided below: 2021 2022 2023 Costs incurred during the year Estimated costs to complete as of year end Billings during the year Cash Collections during the year $4,800,000 $7,200,000 $4,400,000 11,200,000 4,000,000 4,000,000 8,000,000 8,000,000 3,600,000 7,200,000 9,200,000 Kokosing recognizes revenue over time according to percentage of completion. Required: 1. Compute the amount of revenue and gross profit to be recognized in 2021, 2022, and 2023. 2. Prepare the necessary journal entries for 2021 and 2022. Use the following accounts for your journal entries - "Construction in Progress", "Cash, Materials etc.", "Accounts Receivable", "Billings on Construction in Progress", "Cash", "Cost of Construction", and "Revenue from Long-term contracts". 3. Prepare a partial…
- Beck Construction Company began work on a new building project on January 1, 2023. The project is to be completed by December 31, 2025, for a fixed price of $149 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years 2023 2024 2025 Actual costs incurred in each year $ 42 million $ 69 million, $ 47 million Required: What amount of gross profit (or loss) would Beck record on this project in each year, assuming that Beck recognizes revenue for this project upon completion of the project? Years 2023 2024 2025 Note: Enter "None" if there is no requirement of recognizing profit or loss. Loss amounts should be indicated with a minus sign. Enter your answers in millions (1.e., 10,000,000 should be entered as 10). Estimated remaining costs to complete the project (measured at December 31 of each year) $ 84 million $ 69 million $0 million Gross Profit (or Loss) recognized million million…On January 1, 2024, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2025. Expenditures on the project were as follows: January 1, 2024 March 1, 2024 June 30, 2024 October 1, 2024 January 31, 2025 April 30, 2025 August 31, 2025 $1,000,000 600,000 800,000 600,000 270,000 585,000 900,000 On January 1, 2024, the company obtained a $3 million construction loan with a 10% interest rate. The loan was outstanding all of 2024 and 2025. The company's other interest-bearing debt included two long-term notes of $4,000,000 and $6,000,000 with interest rates of 6% and 8%, respectively. Both notes were outstanding during all of 2024 and 2025. Interest is paid annually on all debt. The company's fiscal year-end is December 31. 4. Compute the cost to be allocated to the building in 2025 other than Capitalized Interest, Show your computation in the workpaper provided. 4. 1/31/2025 4/30/2025 8/31/2025…s
- In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 $1,400,000 2025 2026 $3,150,000 $2,695,000 Cost incurred during the year Estimated costs to complete as of year-end 5,600,000 2,450,000 0 Billings during the year 1,000,000 3,550,000 5,450,000 Cash collections during the year 800,000 2,600,000 6,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.Suppose a company spends $100,000 on research and development in 2021. As a result of the products developed, additional revenue is generated over the next five years totaling $600,000. When is the cost of the research and development in 2021 recognized as an expense? Multiple Choice Evenly over the period 2022-2026. Full amount in 2026. Evenly over the period 2021-2025. Full amount in 2021.On February 1, 2023, Sandhill Contractors agreed to construct a building at a contract price of $3,460,000. The total estimated construction costs would be $1,890,000 and the project would be finished in 2025. Information relating to the costs and billings for this contract is as follows: Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date 2023 Gross profit/ (loss) 689,850 1,200,150 1,100,000 1,000,000 2023 2024 573050 $1,162,000 $ 2,365,000 913,000 1,890,000 1,750,000 2025 Calculate the gross profit / (loss) that should be recognized for 2023, 2024, and 2025 using the percentage completion method. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round percentage complete to 1 decimal place, e.g. 15.2% and final answers to O decimal places, e.g. 5,125.) 2024 -0- 3,460,000 2,950,000 -107450 $ LA 2025 40450
- In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion. 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).2-c. In the journal below, complete the necessary journal entries for the year 2023…Y3U.S. Metallurgical Inc. reported the following balances in its financial statements and disclosure notes at December 31, 2020. Plan assets $ 400,000 Projected benefit obligation 320,000 U.S.M.'s actuary determined that 2021 service cost is $60,000. Both the expected and actual rate of return on plan assets are 9%. The interest (discount) rate is 5%. U.S.M. contributed $120,000 to the pension fund at the end of 2021, and retirees were paid $44,000 from plan assets. (Enter your answers in thousands (i.e., 10,000 should be entered as 10).) Required: What is the pension expense at the end of 2021? What is the projected benefit obligation at the end of 2021? What is the plan assets balance at the end of 2021? What is the net pension asset or net pension liability at the end of 2021? Prepare journal entries to record the (a) pension expense, (b) funding of plan assets, and (c) retiree benefit payments.