n 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The pad was completed in 2023. Information related to the contract is as follows: 2021 $ 2,184,000 5,616,000 1,800,000 1,600,000 2022 2023 $2,316,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $ 3,510,000 2,106,000 3,894,000 3,400,000 4,306,000 5,000, 000 ssume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. equired: .Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. -a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs ncurred). -b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs ncurred). -c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs ncurred). . Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the ontract. . Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs ncurred and costs to complete information.
n 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The pad was completed in 2023. Information related to the contract is as follows: 2021 $ 2,184,000 5,616,000 1,800,000 1,600,000 2022 2023 $2,316,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $ 3,510,000 2,106,000 3,894,000 3,400,000 4,306,000 5,000, 000 ssume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. equired: .Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. -a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs ncurred). -b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs ncurred). -c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs ncurred). . Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the ontract. . Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs ncurred and costs to complete information.
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
Need part 1, 2a, 2b, 2c please
1. Calculate the amount of revenue and gross
2-a. In the journal below, complete the necessary
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).
![**Westgate Construction Company Contract Overview**
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
**Contract Financial Details:**
- **2021:**
- Cost incurred during the year: $2,184,000
- Estimated costs to complete as of year-end: $5,616,000
- Billings during the year: $1,800,000
- Cash collections during the year: $1,680,000
- **2022:**
- Cost incurred during the year: $3,510,000
- Estimated costs to complete as of year-end: $2,106,000
- Billings during the year: $3,600,000
- Cash collections during the year: $3,960,000
- **2023:**
- Cost incurred during the year: $2,316,000
- Estimated costs to complete as of year-end: $0
- Billings during the year: $4,386,000
- Cash collections during the year: $5,000,000
Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.
**Required Tasks:**
1. **Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.**
2. **Journal Entries:**
- Complete the necessary journal entries for the year 2021.
- Complete the necessary journal entries for the year 2022.
- Complete the necessary journal entries for the year 2023.
3. **Prepare a Partial Balance Sheet:**
- Complete the required information for the years 2021 and 2022 showing any items related to the contract.
4. **Revenue and Gross Profit Calculation:**
- Calculate the revenue and gross profit (loss) to be recognized in each of the three years based on incurred costs and costs to complete information.
**Costs Details for Calculation:**
- **2021:**
- Cost incurred during the year: $2,520,000
- Estimated costs to complete as of year-end: $5,720,000
- **2022:**
- Cost incurred during the](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F4a92e595-69a8-4ba3-9e62-d1ba59e7a231%2F79188697-c1ff-44e7-bfd3-0dd381351664%2Fn4ma6ia_processed.png&w=3840&q=75)
Transcribed Image Text:**Westgate Construction Company Contract Overview**
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
**Contract Financial Details:**
- **2021:**
- Cost incurred during the year: $2,184,000
- Estimated costs to complete as of year-end: $5,616,000
- Billings during the year: $1,800,000
- Cash collections during the year: $1,680,000
- **2022:**
- Cost incurred during the year: $3,510,000
- Estimated costs to complete as of year-end: $2,106,000
- Billings during the year: $3,600,000
- Cash collections during the year: $3,960,000
- **2023:**
- Cost incurred during the year: $2,316,000
- Estimated costs to complete as of year-end: $0
- Billings during the year: $4,386,000
- Cash collections during the year: $5,000,000
Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.
**Required Tasks:**
1. **Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.**
2. **Journal Entries:**
- Complete the necessary journal entries for the year 2021.
- Complete the necessary journal entries for the year 2022.
- Complete the necessary journal entries for the year 2023.
3. **Prepare a Partial Balance Sheet:**
- Complete the required information for the years 2021 and 2022 showing any items related to the contract.
4. **Revenue and Gross Profit Calculation:**
- Calculate the revenue and gross profit (loss) to be recognized in each of the three years based on incurred costs and costs to complete information.
**Costs Details for Calculation:**
- **2021:**
- Cost incurred during the year: $2,520,000
- Estimated costs to complete as of year-end: $5,720,000
- **2022:**
- Cost incurred during the
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education