MS Project Assignment Project Scenario School of Computing and Technology wants a new website for its use and your company won the contract to handle the project. As a project manager, you are to assemble your team, analyse the needs for the project, develop a schedule, decide on the tasks, assign resources to tasks, track the progress, manage the budget and analyse the workloads of the project using Microsoft project application. +The following table lists some of the project requirements: Task Name Planning Client-meeting Client-requirement Analysis | Duration| Predecessors | Resource Names 13 days 1 day 2 days 3 days 1 wk. 11 days 4 days 1 wk 1 day 26 days 3 wks 1 Project manager Project manager, Content manager Project manager, Content manager Project manager 2 3 2FS+2 days 4 3 5 Collect data 4 Design Interface layout Prototype design Design signoff 10 Development Coding Layout maintenance 2 wks Client feedback 14 Launch 15 6. 5,1 Interface designer, Software[1],Hardware(1) Hardware(1],Software(1],Interface designer Project manager 7 8 7 9. 8FS+1 day 9,6 Developer, Software[1],Hardware[1],Animator Hardware(1],Software(1],Content manager Project manager, Content manager 11 12 11 1 day 6 days 2 days 13 12 13,10 Design quality Content manager, Project managrer Content manager, Developer, Software(1),Hardware[1] Content manager, Project manager Software(1),Hardware(1),Content manager 16 Testing 2 days 15 Approval 3 days 2 wks O days 16FS-1 day 17,14 17 18 Maintenance 19 End project 18
MS Project Assignment Project Scenario School of Computing and Technology wants a new website for its use and your company won the contract to handle the project. As a project manager, you are to assemble your team, analyse the needs for the project, develop a schedule, decide on the tasks, assign resources to tasks, track the progress, manage the budget and analyse the workloads of the project using Microsoft project application. +The following table lists some of the project requirements: Task Name Planning Client-meeting Client-requirement Analysis | Duration| Predecessors | Resource Names 13 days 1 day 2 days 3 days 1 wk. 11 days 4 days 1 wk 1 day 26 days 3 wks 1 Project manager Project manager, Content manager Project manager, Content manager Project manager 2 3 2FS+2 days 4 3 5 Collect data 4 Design Interface layout Prototype design Design signoff 10 Development Coding Layout maintenance 2 wks Client feedback 14 Launch 15 6. 5,1 Interface designer, Software[1],Hardware(1) Hardware(1],Software(1],Interface designer Project manager 7 8 7 9. 8FS+1 day 9,6 Developer, Software[1],Hardware[1],Animator Hardware(1],Software(1],Content manager Project manager, Content manager 11 12 11 1 day 6 days 2 days 13 12 13,10 Design quality Content manager, Project managrer Content manager, Developer, Software(1),Hardware[1] Content manager, Project manager Software(1),Hardware(1),Content manager 16 Testing 2 days 15 Approval 3 days 2 wks O days 16FS-1 day 17,14 17 18 Maintenance 19 End project 18
Computer Networking: A Top-Down Approach (7th Edition)
7th Edition
ISBN:9780133594140
Author:James Kurose, Keith Ross
Publisher:James Kurose, Keith Ross
Chapter1: Computer Networks And The Internet
Section: Chapter Questions
Problem R1RQ: What is the difference between a host and an end system? List several different types of end...
Related questions
Question
microsoft project assignment
![MS Project Assignment
Project Scenario
School of Computing and Technology wants a new website for its use and your
company won the contract to handle the project. As a project manager, you are to
assemble your team, analyse the needs for the project, develop a schedule, decide
on the tasks, assign resources to tasks, track the progress, manage the budget and
analyse the workloads of the project using Microsoft project application.
+ The following table lists some of the project requirements:
Predecessors Resource Names
Task Name
Duration
Planning
Client-meeting
Client-requirement
Analysis
1
13 days
1 day
Project manager
Project manager, Content manager
Project manager, Content manager
Project manager
2 days
3 days
1 wk
11 days
4 days
1 yk
1 day
26 days
3 wks
Layout maintenance 2 wks
1 day
6 days
2 days
3
2FS+2 days
4
3
Collect data
4
Design
Interface layout
5,1
Interface designer, Software[1],Hardware[1]
Hardware[1],Software[1],Interface designer
Project manager
7
Prototype design
Design signoff
10 Development
8.
7
8FS+1 day
9,6
Developer, Software[1],Hardware[1],Animator
Hardware[1],Software[1],Content manager
Project manager, Content manager
11
Coding
12
11
13
Client feedback
12
14 Launch
13,10
Content manager, Project manager
Content manager, Developer,
Software(1],Hardware(1]
Content manager, Project manager
Software[1),Hardware[1],Content manager
15
Design quality
16
Testing
2 days
15
3 days
2 wks
O days
16FS-1 day
17,14
17
Approval
18 | Maintenance
19 End project
18](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Faedcb8c1-a85a-4c48-97b7-cd937673253c%2Ff49e17cf-17f3-481e-bd53-8751a65464fa%2F5ts5jxb_processed.png&w=3840&q=75)
Transcribed Image Text:MS Project Assignment
Project Scenario
School of Computing and Technology wants a new website for its use and your
company won the contract to handle the project. As a project manager, you are to
assemble your team, analyse the needs for the project, develop a schedule, decide
on the tasks, assign resources to tasks, track the progress, manage the budget and
analyse the workloads of the project using Microsoft project application.
+ The following table lists some of the project requirements:
Predecessors Resource Names
Task Name
Duration
Planning
Client-meeting
Client-requirement
Analysis
1
13 days
1 day
Project manager
Project manager, Content manager
Project manager, Content manager
Project manager
2 days
3 days
1 wk
11 days
4 days
1 yk
1 day
26 days
3 wks
Layout maintenance 2 wks
1 day
6 days
2 days
3
2FS+2 days
4
3
Collect data
4
Design
Interface layout
5,1
Interface designer, Software[1],Hardware[1]
Hardware[1],Software[1],Interface designer
Project manager
7
Prototype design
Design signoff
10 Development
8.
7
8FS+1 day
9,6
Developer, Software[1],Hardware[1],Animator
Hardware[1],Software[1],Content manager
Project manager, Content manager
11
Coding
12
11
13
Client feedback
12
14 Launch
13,10
Content manager, Project manager
Content manager, Developer,
Software(1],Hardware(1]
Content manager, Project manager
Software[1),Hardware[1],Content manager
15
Design quality
16
Testing
2 days
15
3 days
2 wks
O days
16FS-1 day
17,14
17
Approval
18 | Maintenance
19 End project
18

Transcribed Image Text:Resource Information:
Resource Name
Туре
Group
Max. Units
Std. Rate
Project manager
Work
Phase 1
100%
£100.00/hr
Interface designer
Work
Phase 2
150%
£100.00/hr
3
Animator
Work
Phase 2
£150.00/hr
100%
Content manager
Work
Phase 1
200%
£200.00/hr
5
Developer
Work
Phase 3
£250.00/hr
150%
6
Graphics designer
Work
Phase 2
£300.00/hr
150%
7
Software
Work
100%
£50.00/hr
8
Hardware
Work
100%
£50.00/hr
Other Project Information:
• Project Start date: Friday 13 August 2021.
• Set the meeting schedule to automatic.
• Schedule the project from the project start date.
• Precedence is the classical finish-to-start.
• Non-working days: 30 August 2021 and 31 August 2021
• Insert a deadline to the last task (Project Deadline: 17.11.2021).
• Link the task to see the milestone.
GNATT DIAGRAM
2.
4.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images

Recommended textbooks for you

Computer Networking: A Top-Down Approach (7th Edi…
Computer Engineering
ISBN:
9780133594140
Author:
James Kurose, Keith Ross
Publisher:
PEARSON

Computer Organization and Design MIPS Edition, Fi…
Computer Engineering
ISBN:
9780124077263
Author:
David A. Patterson, John L. Hennessy
Publisher:
Elsevier Science

Network+ Guide to Networks (MindTap Course List)
Computer Engineering
ISBN:
9781337569330
Author:
Jill West, Tamara Dean, Jean Andrews
Publisher:
Cengage Learning

Computer Networking: A Top-Down Approach (7th Edi…
Computer Engineering
ISBN:
9780133594140
Author:
James Kurose, Keith Ross
Publisher:
PEARSON

Computer Organization and Design MIPS Edition, Fi…
Computer Engineering
ISBN:
9780124077263
Author:
David A. Patterson, John L. Hennessy
Publisher:
Elsevier Science

Network+ Guide to Networks (MindTap Course List)
Computer Engineering
ISBN:
9781337569330
Author:
Jill West, Tamara Dean, Jean Andrews
Publisher:
Cengage Learning

Concepts of Database Management
Computer Engineering
ISBN:
9781337093422
Author:
Joy L. Starks, Philip J. Pratt, Mary Z. Last
Publisher:
Cengage Learning

Prelude to Programming
Computer Engineering
ISBN:
9780133750423
Author:
VENIT, Stewart
Publisher:
Pearson Education

Sc Business Data Communications and Networking, T…
Computer Engineering
ISBN:
9781119368830
Author:
FITZGERALD
Publisher:
WILEY