('Mojag pakorlein In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 $3,150,000 $2,475,000 2,250,000 3, 100, 000 3,100,e00 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,100,000 5,400,000 2,150,000 1,875,000 4,750,000 5,025,000 Westgate recognizes revenue over time according to percentage of completion.

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 9MC
icon
Related questions
Question
explain in Full detail.
uapiayeu uelow.j
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021
2022
$3,150,000 $2,475, 000
2023
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
$2,100,000
5,400,000
2,150, 000
1,875,000
2,250,000
3,100,000
3,100,000
4,750,000
5,025,000
Westgate recognizes revenue over time according to percentage of completion.
Transcribed Image Text:uapiayeu uelow.j In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 $3,150,000 $2,475, 000 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,100,000 5,400,000 2,150, 000 1,875,000 2,250,000 3,100,000 3,100,000 4,750,000 5,025,000 Westgate recognizes revenue over time according to percentage of completion.
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the
contract. (Do not round intermediate calculations.)
Balance Sheet (Partial)
2021
2022
Current assets:
Accounts receivable
Construction in progress
Less. Billings
Costs and profit in excess of billings
Current liabilities
Transcribed Image Text:3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) Balance Sheet (Partial) 2021 2022 Current assets: Accounts receivable Construction in progress Less. Billings Costs and profit in excess of billings Current liabilities
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Basic Accounting Terms
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L