MD Construction entered into a contract beginning January 1, 2010 to build a parking complex. It has been estimated that the complex will cost P600,000 and will take three years to construct. The complex will be billed at P900,000. The following data pertain to the construction period. 2010 2011 2012 Cost to date P270,000 P420,000 P600,000 Estimated cost to complete Progress billings to date 330,000 180,000 550,000 -0- 270,000 240,000 900,000 Cash collected to date 500,000 900,00 During 2010, costs incurred include P30,000 standard materials stored at the site to be used in 2012 to complete the project. Using percentage-of-completion method, compute the gross profit that should be recognized in 2011:

Financial Accounting Intro Concepts Meth/Uses
14th Edition
ISBN:9781285595047
Author:Weil
Publisher:Weil
Chapter8: Revenue Recognition, Receivables, And Advances From Customers
Section: Chapter Questions
Problem 35E
icon
Related questions
Topic Video
Question
a. 75,000
b. 195,000
c. 120,000
d. 300,000
MD Construction entered into a contract beginning January 1, 2010 to build a parking
complex. It has been estimated that the complex will cost P600,000 and will take three
years to construct. The complex will be billed at P900,000. The following data pertain to
the construction period.
2010
2011
2012
Cost to date
P270,000 P420,000 P600,000
Estimated cost to complete
Progress billings to date
Cash collected to date
330,000
270,000
180,000
-0-
550,000
900,000
240,000
500,000
900,00
During 2010, costs incurred include P30,000o standard materials stored at the site to be
used in 2012 to complete the project. Using percentage-of-completion method,
compute the gross profit that should be recognized in 2011:
Transcribed Image Text:MD Construction entered into a contract beginning January 1, 2010 to build a parking complex. It has been estimated that the complex will cost P600,000 and will take three years to construct. The complex will be billed at P900,000. The following data pertain to the construction period. 2010 2011 2012 Cost to date P270,000 P420,000 P600,000 Estimated cost to complete Progress billings to date Cash collected to date 330,000 270,000 180,000 -0- 550,000 900,000 240,000 500,000 900,00 During 2010, costs incurred include P30,000o standard materials stored at the site to be used in 2012 to complete the project. Using percentage-of-completion method, compute the gross profit that should be recognized in 2011:
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting Equation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Financial Reporting, Financial Statement Analysis…
Financial Reporting, Financial Statement Analysis…
Finance
ISBN:
9781285190907
Author:
James M. Wahlen, Stephen P. Baginski, Mark Bradshaw
Publisher:
Cengage Learning