Manufacturing overhead incurred Direct manufacturing labour costs Machine Hours Machining Dept. Finishing Dept. $11,200,000 950,000 220,000 $ $7,900,000 $4,100,000 32,000 Compute the manufacturing overhead variance for each department and for the Dover plant as a whole.
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Please help me with show all Calculation thanku