Mannerman Products, Incorporated, operates an electric power plant which provides all electrical power for the company's Machining and Fabrication departments. Information on kilowatt- hours (kwh) of power usage in these departments for May follow: Machining Fabrication Total 20,000 10,000 30,000 Budgeted kwh Actual kwh ● The costs of the electric power plant are all fixed. Budgeted fixed costs for May totaled $60,000 and are determined by peak- period requirements. Actual fixed costs for the month totaled $65,000. The Machining Department requires 60% of the peak- period capacity and the Fabrication Department requires 40%. 25,000 How much (if any) of the electric power plant's actual fixed costs of $65,000 should not be charged to the other departments? Multiple Choice ● $0 ● • $10,000 ● 15,000 40,000 $5,000 $15,000
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Please do not give solution in image format thanku
![Mannerman Products, Incorporated,
operates an electric power plant which
provides all electrical power for the
company's Machining and Fabrication
departments. Information on kilowatt-
hours (kwh) of power usage in these
departments for May follow:
Machining Fabrication Total
20,000
10,000 30,000
Budgeted
kwh
Actual
kwh
The costs of the electric power plant are all
fixed. Budgeted fixed costs for May totaled
$60,000 and are determined by peak-
period requirements. Actual fixed costs for
the month totaled $65,000. The Machining
Department requires 60% of the peak-
period capacity and the Fabrication
Department requires 40%.
●
• $0
How much (if any) of the electric power
plant's actual fixed costs of $65,000 should
not be charged to the other departments?
Multiple Choice
●
25,000 15,000
●
●
40,000
$10,000
$5,000
$15,000](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fb0a2b3c0-f69b-4bac-bc67-35acaf063f53%2F47cd0bde-d028-4053-9ed4-8d6c33157817%2Fcbmllr_processed.jpeg&w=3840&q=75)
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)