Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 25 percent capacity cushion is best. Component A B C Time Standard Processing (hr/unit) 0.04 0.30 0.05 Setup (hr/lot) 1.0 4.2 8.7 Lot Size (units/lot) 40 80 120 Demand Forecast Pessimistic Expected Optimistic Pessimistic 14,000 10,000 17,000 Demand Forecast a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up to the next whole number.) Capacity Requirement (M) machines machines machines Expected 17,000 13,000 23,000 Optimistic 25,000 18,000 40,000
Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 25 percent capacity cushion is best. Component A B C Time Standard Processing (hr/unit) 0.04 0.30 0.05 Setup (hr/lot) 1.0 4.2 8.7 Lot Size (units/lot) 40 80 120 Demand Forecast Pessimistic Expected Optimistic Pessimistic 14,000 10,000 17,000 Demand Forecast a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up to the next whole number.) Capacity Requirement (M) machines machines machines Expected 17,000 13,000 23,000 Optimistic 25,000 18,000 40,000
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Don't used Chat gpt
![Macon Controls produces three different types of control units used to protect industrial equipment from overheating.
Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant
operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at
the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations
manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 25
percent capacity cushion is best.
Component
A
B
C
ample
Time Standard
Processing
(hr/unit)
0.04
0.30
0.05
Setup
(hr/lot)
1.0
4.2
8.7
Get more help.
Lot Size
(units/lot)
40
80
120
Demand Forecast
a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and
maximum (Optimistic) demand? (Enter your responses rounded up to the next whole number.)
Pessimistic
Expected
Optimistic
Pessimistic
14,000
10,000
17,000
Demand Forecast
Capacity
Requirement (M)
machines
machines
machines
Expected
17,000
13,000
23,000
Optimistic
25,000
18,000
40,000
Clear all
Check answer](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Ff4bafa34-87e2-4b89-a00d-0a3bf0e8ad27%2F63d9d23d-eae2-4469-a6c6-d0220b92070d%2Frwpql7_processed.png&w=3840&q=75)
Transcribed Image Text:Macon Controls produces three different types of control units used to protect industrial equipment from overheating.
Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant
operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at
the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations
manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 25
percent capacity cushion is best.
Component
A
B
C
ample
Time Standard
Processing
(hr/unit)
0.04
0.30
0.05
Setup
(hr/lot)
1.0
4.2
8.7
Get more help.
Lot Size
(units/lot)
40
80
120
Demand Forecast
a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and
maximum (Optimistic) demand? (Enter your responses rounded up to the next whole number.)
Pessimistic
Expected
Optimistic
Pessimistic
14,000
10,000
17,000
Demand Forecast
Capacity
Requirement (M)
machines
machines
machines
Expected
17,000
13,000
23,000
Optimistic
25,000
18,000
40,000
Clear all
Check answer
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.