Krizum Industries makes heavy construction equipment. The standard for a particular crane calls for 17 direct labor-hours at $15 per direct labor-hour. During a recent period, 1,150 cranes were made. The labor rate variance was zero and the labor efficiency variance was $4,800 unfavorable. How many actual direct labor-hours were worked?
Krizum Industries makes heavy construction equipment. The standard for a particular crane calls for 17 direct labor-hours at $15 per direct labor-hour. During a recent period, 1,150 cranes were made. The labor rate variance was zero and the labor efficiency variance was $4,800 unfavorable. How many actual direct labor-hours were worked?
Chapter8: Standard Costs And Variances
Section: Chapter Questions
Problem 7PB: Marymount Company makes one product. In the month of April, it made 3,500 units. Workers were paid...
Related questions
Question
Krizum industries makes...accounting question

Transcribed Image Text:Krizum Industries makes heavy construction equipment. The
standard for a particular crane calls for 17 direct labor-hours at
$15 per direct labor-hour. During a recent period, 1,150 cranes
were made. The labor rate variance was zero and the labor
efficiency variance was $4,800 unfavorable.
How many actual direct labor-hours were worked?
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College