Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Total Cost Normal Time Crash Time Normal with Immediate Activity (weeks) (weeks) Cost Crashing Predecessor(s) A 3 $1,400 $2,100 B 2. 1 $2,000 $2,800 C 1 $300 $300 $1,680 $1,050 $5,750 $2,300 A $1,400 $900 3. 6. 3 1 $4,250 C 4 $1,800 DE a) Based on the given information regarding the activities for the project, the project completion date = weeks. b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing the activities: The first activity to crash is by 2 weeks at a per week crashing cost of dollars. Next, one should crash activity D and activity v by 2 weeks for an additional total per week crashing cost of dollars. c) New requirements are to reduce the project to 7 weeks. Continuing to crash the activities from 10 weeks based on the above crashing already completed, the following is the order for crashing: Next activity to crash in order is V by 2 weeks at a per week crashing cost of dollars. Next, one should crash activity and activity E by 1 week at a total per week crashing cost of dollars. Enter your answer in each of the answer boxes.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Question Help
Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens.
The activities necessary to build an experimental model and related data are listed in the following table:
Total Cost
Normal Time
Crash Time Normal
with
Immediate
Activity
(weeks)
(weeks)
Cost
Crashing Predecessor(s)
$1,400
$2,000
$2,100
$2,800
A
3
2.
1
C
1
$300
$300
A
$1,400
$900
$1,680
$1,050
$5,750
D
7
E
$4,250
$1,800
F
1
G
4
$2,300
D, E
weeks.
a) Based on the given information regarding the activities for the project, the project completion date =
b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing the activities:
The first activity to crash is
by 2 weeks at a per week crashing cost of
dollars.
Next, one should crash activity D and activity
by 2 weeks for an additional total per week crashing cost of
dollars.
c) New requirements are to reduce the project to 7 weeks. Continuing to crash the activities from 10 weeks based on the above crashing already completed, the
following is the order for crashing:
Next activity to crash in order is
V by 2 weeks at a per week crashing cost of
dollars.
Next, one should crash activity
and activity E by 1 week at a total per week crashing cost of
dollars.
Enter your answer in each of the answer boxes.
133
Transcribed Image Text:Question Help Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Total Cost Normal Time Crash Time Normal with Immediate Activity (weeks) (weeks) Cost Crashing Predecessor(s) $1,400 $2,000 $2,100 $2,800 A 3 2. 1 C 1 $300 $300 A $1,400 $900 $1,680 $1,050 $5,750 D 7 E $4,250 $1,800 F 1 G 4 $2,300 D, E weeks. a) Based on the given information regarding the activities for the project, the project completion date = b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing the activities: The first activity to crash is by 2 weeks at a per week crashing cost of dollars. Next, one should crash activity D and activity by 2 weeks for an additional total per week crashing cost of dollars. c) New requirements are to reduce the project to 7 weeks. Continuing to crash the activities from 10 weeks based on the above crashing already completed, the following is the order for crashing: Next activity to crash in order is V by 2 weeks at a per week crashing cost of dollars. Next, one should crash activity and activity E by 1 week at a total per week crashing cost of dollars. Enter your answer in each of the answer boxes. 133
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Knowledge Booster
Forecasting methods
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.