Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of September but needed an additional $3,000 of direct materials and additional direct labor of $6,500 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred. What is the total cost of the job when it is completed in October? A. $16,000 B. $22,500 C. $37,000 D. $26,500 E. $32,000
Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of September but needed an additional $3,000 of direct materials and additional direct labor of $6,500 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred. What is the total cost of the job when it is completed in October? A. $16,000 B. $22,500 C. $37,000 D. $26,500 E. $32,000
Related questions
Question
can you please solve this

Transcribed Image Text:Job A3B was ordered by a customer on September 25. During the
month of September, Jaycee Corporation requisitioned $2,500 of
direct materials and used $4,000 of direct labor. The job was not
finished by the end of September but needed an additional $3,000 of
direct materials and additional direct labor of $6,500 to finish the job
in October. The company applies overhead at the end of each month
at a rate of 200% of the direct labor cost incurred. What is the total
cost of the job when it is completed in October?
A. $16,000
B. $22,500
C. $37,000
D. $26,500
E. $32,000