January 1, 2019, A contract with a 6 percent retainage clause was sig ned with Arab Construction Company to construct a new dly Kall F8 $4,000,000. March 15, The contractor submitted a progress billing of $3,000,000; the billing (less a 6 percent retainage) was approved. The entr that should be recorded in March 15 is O a. Debit, Budgetary Fund Reserved for Encumbrances $3,000,000; Cr dit, Encumbrances $3,000,000 O b. Debit, Encumbrances $3,000,000; Credit, Budgetary Fund Reserver for Encumbrances $3,000,000. O. Debit, Encumbrances $4,000,000; Credit, Budgetary Fund Reserver for Encumbrances $4,000,000. O d. Debit, Expenditures-Construction Cost $3,000,000; Credit, Vouche Payable $3,000,000,

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
January 1, 2019, A contract with a 6 percent retainage clause was sic ned with Arab Construction Company to construct a new city hall for
$4,000,000. March 15, The contractor submitted a progress billing of $3,000,000; the billing (less a 6 percent retainage) was approved. The entry
that should be recorded in March 15 is
O a. Debit, Budgetary Fund Reserved for Encumbrances $3,000,000; Cr dit, Encumbrances $3,000,000
O b. Debit, Encumbrances $3,000,000; Credit, Budgetary Fund Reserver for Encumbrances $3,000,000.
O. Debit, Encumbrances $4,000,000; Credit, Budgetary Fund Reservec for Encumbrances $4,000,000.
O d. Debit, Expenditures-Construction Cost $3,000,000; Credit, Vouche Payable $3,000,000,
Transcribed Image Text:January 1, 2019, A contract with a 6 percent retainage clause was sic ned with Arab Construction Company to construct a new city hall for $4,000,000. March 15, The contractor submitted a progress billing of $3,000,000; the billing (less a 6 percent retainage) was approved. The entry that should be recorded in March 15 is O a. Debit, Budgetary Fund Reserved for Encumbrances $3,000,000; Cr dit, Encumbrances $3,000,000 O b. Debit, Encumbrances $3,000,000; Credit, Budgetary Fund Reserver for Encumbrances $3,000,000. O. Debit, Encumbrances $4,000,000; Credit, Budgetary Fund Reservec for Encumbrances $4,000,000. O d. Debit, Expenditures-Construction Cost $3,000,000; Credit, Vouche Payable $3,000,000,
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education