Iternatives are being considered. Alternative 1 - One-stage construction: Build a four lane bridge right now for $377,000. Alternative 2 - Two-stage construction: Start with a two-lane bridge now for $180,000 and widen to four lanes later when traffic justifies. The future cost of widening the bridge to four-lanes at that time will be $180,000 plus an extra $25,000 for every year that widening is delayed. For example, if future widening is done at the end of year 7, the cost of widening at that time will be equal to $180,000 + 7x($25,000) = $355,000. The following estimates have been made of when widening to a four-lane bridge will be required: End of year 5 End of year 7 End of year 9 Pessimistic estimate Most likely estimate Optimistic estimate a) Calculate the PW of costs for the different scenarios of Alternative 2 PWpessimistic (9%)= $ thousand (Round to one decimal place.) PWmost likely (9%) = $| thousand (Round to one decimal place.) PWoptimistic tic(9%) = $| thousand (Round to one decimal place.) b) Calculate the expected PW costs of Alternative 2 using the "three-point estimation" technique Expected PW = $ thousand (Round to one decimal place.) c) Based on these estimates, which alternative is more economical?
Iternatives are being considered. Alternative 1 - One-stage construction: Build a four lane bridge right now for $377,000. Alternative 2 - Two-stage construction: Start with a two-lane bridge now for $180,000 and widen to four lanes later when traffic justifies. The future cost of widening the bridge to four-lanes at that time will be $180,000 plus an extra $25,000 for every year that widening is delayed. For example, if future widening is done at the end of year 7, the cost of widening at that time will be equal to $180,000 + 7x($25,000) = $355,000. The following estimates have been made of when widening to a four-lane bridge will be required: End of year 5 End of year 7 End of year 9 Pessimistic estimate Most likely estimate Optimistic estimate a) Calculate the PW of costs for the different scenarios of Alternative 2 PWpessimistic (9%)= $ thousand (Round to one decimal place.) PWmost likely (9%) = $| thousand (Round to one decimal place.) PWoptimistic tic(9%) = $| thousand (Round to one decimal place.) b) Calculate the expected PW costs of Alternative 2 using the "three-point estimation" technique Expected PW = $ thousand (Round to one decimal place.) c) Based on these estimates, which alternative is more economical?
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
Related questions
Question
4
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
Recommended textbooks for you
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education