Instructions. For the given data, provide the following. • Complete Network Diagram highlighting the critical path and showing ES, LS, EF, LF Identify the paths, their duration and slack Provide the table showing ES, LS, EF, LF. TF. FF and remarks. Given: A. B, and C are starting activities D follows A while E follows C B. D and E precede J Kand F cannot start until B, D and E are completed G follows Cand precedes H and I H and I cannot proceed until F is completed L follows K and precedes N • J precedes P, M and S H. I. and P must be completed before Q can start Land M must be completed before N can start • O follows N while R follows Q R, O and S are ending activities Dummy activity x is provided after activity I NORMAL TIME ACTIVITY ES LS EF LF TF FF REMARKS 12 D E 4. 4. 10 M

Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter4: Engineering Communication
Section: Chapter Questions
Problem 24P: Present Example 7.4 in Chapter 7 using the format discussed in Section 4.2. Divide the example...
icon
Related questions
Question
Instructions. For the given data, provide the following.
Complete Network Diagram highlighting the critical path and showing ES, LS, EF, LF
Identify the paths, their duration and slack
Provide the table showing ES, LS, EF, LF. TF. FF and remarks.
Given:
A, B, and Care starting activities
D follows A while E follows C
B. D and E precede J
Kand F cannot start until B, D and E are completed
• G follows C and precedes H and I
H and I cannot proceed until Fis completed
Lfollows K and precedes N
• J precedes P, M and S
H. I. and P must be completed before Q can start
Land M must be completed before N can start
O follows N while R follows Q
R,O and S are ending activities
Dummy activity x is provided after activity I
NORMAL
TIME
ACTIVITY
ES
LS
EF
LF
TF
FF
REMARKS
12
5n
3.
4.
10
M.
6.
3.
Transcribed Image Text:Instructions. For the given data, provide the following. Complete Network Diagram highlighting the critical path and showing ES, LS, EF, LF Identify the paths, their duration and slack Provide the table showing ES, LS, EF, LF. TF. FF and remarks. Given: A, B, and Care starting activities D follows A while E follows C B. D and E precede J Kand F cannot start until B, D and E are completed • G follows C and precedes H and I H and I cannot proceed until Fis completed Lfollows K and precedes N • J precedes P, M and S H. I. and P must be completed before Q can start Land M must be completed before N can start O follows N while R follows Q R,O and S are ending activities Dummy activity x is provided after activity I NORMAL TIME ACTIVITY ES LS EF LF TF FF REMARKS 12 5n 3. 4. 10 M. 6. 3.
Expert Solution
steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Knowledge Booster
Work breakdown structure
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning